Ensure you have the correct version running!
If you don't see 26.22 in the bottom left corner, please clear your browser cache.
Note: If a new feature is not visible, you may not have the correct access permissions, the option (menu item) may not be enabled on the project, or the feature is otherwise not enabled in e.g. the entity settings.
Please contact your O3 System Admin or Project Admin, or use your organization's O3 support process, if you require access to a new feature.
Highlights: Please check out 'Mind the Gaps' for creating missing packages straight from the CCS.
What's New - Table of Contents
Timesheets
Paper Trail
Timesheets now keep a full change history, so reviewers can see who changed what and when, and who locked or unlocked a timesheet. This gives an audit trail for timesheet data that feeds payroll and payment systems.
Where and How:
Open a timesheet and view its change history, in the same way as change history on other entities.
Details:
Every change to a timesheet field is recorded with the user, timestamp, and old and new values, whether it was made from the detail form, the line items grid, a status change (submit, approve or reject) or a bulk action.
Changes to timesheet line items are included in the timesheet's history.
Lock and unlock actions are recorded with the user and timestamp. See Lock It In in the 26.21 Release Notes.
History is recorded whatever the timesheet's status at the time of the change.
Change history entries cannot be edited or deleted.
No Blanks Allowed
Timesheets can no longer be submitted with incomplete line items, so missing resources and unallocated hours are caught before they reach review.
Where and How:
Applies automatically when a foreperson submits a timesheet, on the web and in ONField.
Details:
Each line item needs a resource name and at least one of an IWP or an other activity (one, the other, or both).
If any line item is incomplete, the whole submit is blocked until it is fixed. A completely empty line item also blocks submit.
Errors appear inline on each affected line item and as a summary for the timesheet.
Saving is not blocked, so a timesheet with incomplete line items can still be saved and finished later.
ONField displays the same validation errors when a timesheet is submitted.
Workface Planning
Plan the Week, Not the Wait
The Weekly Work Plan loads faster on large projects and picks up several usability improvements requested from the field.
Where and How:
Open the Weekly Work Plan as usual; the new filter, column and buttons are available straight away.
An open in new tab button on each IWP lets you enter progress without leaving the plan.
Column selector so you can hide unneeded columns.
More Details:
Faster loading on projects with very large numbers of IWPs.
Filter the plan to a specific IWP.
A new open constraint count column shows which IWPs have constraints that may stop them being planned.
The hours/quantity toggle is now saved with the layout.
Next week's planned value now spreads the work remaining after the selected week across the IWP's remaining working days, so it can no longer exceed what is left. While the selected week is still open, its unearned plan is assumed done that week; for past weeks it carries forward. This applies to both hours and quantity.
Scheduling
A Is for Actual
Gantt start and finish columns now show which kind of date you are looking at, so it is clear at a glance whether a date has happened or is still projected.
Where and How:
Gantt charts. The default Start and Finish columns have been replaced with the new date columns.
Details:
Each date has a leading prefix: A = Actual, F = Forecast, P = Planned (for example, A 20-FEB-2026).
O3 shows the actual date if available, then the forecast date, then the planned date.
A tooltip on each column explains which date type is shown and why.
Engineering
Better Late Than Never
Drawing execution tasks now support backdating progress, matching IWPs, so earned hours land on the date the work was actually done and the Drawing Progress Curve shows an accurate planned-vs-actual picture.
Where and How:
Project Setup -> Project Settings -> Entity Settings -> Drawings -> Enable Backdating Progress. Then set the progress date when recording progress on a drawing's execution task.
A new Progress History view is available from the Drawings view selector.
Details:
Backdating works the same way as on IWPs, including defaults, date limits and role permissions.
Earned hours are attributed to the progress date rather than the date progress was entered, so there is no spike on the day of entry. Planned hours continue to follow the planned schedule.
The progress date stays editable after progress is recorded; changing it moves the earned hours to the new date.
Progress recorded before this release uses its original entry date as the progress date.
Bulk updates can be made via import.
Rolling It Up
The Work Package Progress Curve can now include progress from scope children, so EWP S-curves reflect backdated drawing progress too.
Where and How:
In the Work Package Progress Curve widget settings, enable the new Include Scope Children option (available when Step Completion or Date Earned is selected).
Details:
Execution task progress from scope children, and their own scope children (for example EWP -> DWP -> Drawing), is included alongside the EWP's own execution tasks.
Child progress plots on its actual progress date. Progress on EWP-level tasks plots on its entry date.
Editing a child's progress date updates the curve immediately.
Planned hours continue to follow the planned schedule.
Model
Mind the Gaps
A new Review Missing Packages action finds packages referenced in the CCS that don't yet exist in O3, creates them in bulk, and assigns their components automatically.
Where and How:
From the CCS grid, open the Action menu and choose 'Review Missing Packages'. Select an entity type, then choose the packages to create from the checklist.
Details:
Supported entity types are CWA, CWP, EWP, PWP, TWP and System, one type at a time.
Only packages that are in the CCS but missing from O3 are listed, with a Select All option.
Packages are created via import using the name/ID from the CCS; further details can be edited afterwards in the usual way.
A success/failure summary is shown after creation, with the standard import errors and warnings.
If no packages are missing for the selected type, a message says so.
Components are automatically assigned to the newly created packages.
Paving the Path
CWP-level 4D playback on plot plans now shows CWPs that don't have their own shape, so construction managers can review the path of construction right after generating CWPs from the CWP matrix.
Where and How:
Open a plot plan and run CWP-level 4D playback. Use the new playback setting to choose Review by Discipline or Review by Purpose.
Details:
CWPs with their own shape animate as before, now with an overlaid progress bar.
CWPs without a shape appear as progress bars on their parent CWA's shape.
Bars are labeled with the Discipline or Purpose code, depending on the mode selected. Where there is no abbreviation, the first character is used; CWPs with no Discipline or Purpose show as N/A.
Each bar fills from 0% to 100% across the CWP's planned start to planned finish.
Unshaped CWPs on the same CWA that share a code share one bar, with each CWP weighted evenly.
Unshaped CWPs whose CWA also has no shape are not shown.
Risk Management
By the Numbers
The Risk Register now captures quantitative risk data, so cost and schedule risk analysis can live in O3 rather than a separate spreadsheet.
Where and How:
Open a risk. The new fields appear in the Definition, Cost Impact and Probability and Target Impact and Probability groups of the detail form.
Details:
Categorization: System, Area, Sub-area (filtered by the selected Area; see Areas Within Areas), Discipline, Urgency Level, Impacted P6 Activities (free text) and Intangible Impact.
Pre-mitigation: minimum, most-likely and maximum cost impact, intangible impact and a calculation note. The existing Probability % and minimum/average/maximum projected impact days now sit in the same group.
Mitigation: Mitigation Cost and Mitigation Time (Days).
Post-mitigation: Probability %, minimum, most-likely and maximum cost and schedule impacts, intangible impact, a calculation note, and QSRA Included / QCRA Included checkboxes.
Discipline uses a new project-specific Risk Discipline lookup, separate from the project's engineering Disciplines, so other Discipline dropdowns are unchanged. Urgency Level uses a new Risk Urgency lookup seeded with Emergency, Urgency and Control. Admins can add values to both.
Cost amounts are plain decimals with no currency symbol.
All new fields can be added to the risk grid via the column chooser (hidden by default), filtered, sorted and exported, and populated via the Risk import (lookups resolve by name).
All new fields are optional, and edits are recorded in the risk's change history.
Project Setup
Your Week, Your Way
Weekly views now follow each project's configured week start day instead of a fixed week, so weekly totals match how each project reports.
Where and How:
Navigate to System Admin>Project Admin>Projects>Select Project. Under Project Details, set the week start day on the project details page.
Details:
Applies to dashboard widgets with a weekly date axis (such as Skylines, Progress Curves and History widgets), new weekly timesheets, the crew calendar (including crew hours per weekday) and the Gantt week view.
Progress Cutoff Day remains a separate setting, calculated within weeks as defined by the project's week start day.
Changing the week start day regroups historical data in these views.
Existing timesheets keep their original date ranges, whatever their status; only timesheets created after the change use the new start day.
Each project uses its own week start day.
Take It Back
Work package statuses can now revert automatically when their conditions are no longer met, for example moving back from Complete when progress drops below 100%. This keeps package status consistent with actual progress.
Where and How:
In the entity settings for the work package type, open a status's Allowed Transitions and use the new Revert option. Info bubbles explain the Automatic and Revert options.
Require 100% complete in order to get into "Construction Complete"
If the IWP is in the current status and the preconditions are no longer satisfied, it will revert back to the status.
Details:
Each status can have one revert status.
When an entity is saved and the pre-conditions for its current status are no longer satisfied, it moves to the configured revert status automatically.
The pre-conditions of the revert status are not checked when reverting.
Useful where progress was entered by mistake and later removed.
General
Reply All
Comments have a refreshed, more distinct look, and you can now reply directly to a comment so conversation threads are easier to follow.
Details:
Reply to a specific comment to keep responses together with the comment they answer.