Ensure you have the correct version running!
If you don't see 26.20 in the bottom left corner, please clear your browser cache.
Important - Legacy IWP Sequencing Tool Retired
The legacy IWP Sequencing tool has been removed from the project menu, with IWP Lookahead as its replacement. Old sequencing links now redirect to IWP Lookahead.
Where and How:
IWP Lookahead is located via the Workface Planning menu, then select 'IWP Lookahead'. You then need to select the 'Sequence IWPs' button at the top.
What's New - Table Of Contents
Timesheets
What's Left in the Tank?
Execution tasks and Individual timesheets now show an Available Hours value, calculated as estimated hours minus actual hours. It sits alongside the existing to-go forecast rather than replacing it.
Example:
Details:
Available Hours = Estimated − Actual. For example, a task with 200 estimated and 40 actual hours shows 160 available.
Available Hours updates when actual hours change via the timesheet.
The value appears on the task detail, the task grid, and the individual timesheet.
The forecast "to-go" value continues to display and behave as before.
Available Hours is a calculated value and cannot be edited.
The Whole Day's Work
When a foreperson adds an employee to a crew timesheet, they now see that person's combined daily hours already logged on other timesheets from other projects. This helps avoid double entry and catches time that would otherwise be missed.
Example Employee with timesheet booking shown from other timesheets:
Details:
Adding an employee to a crew timesheet displays their combined total hours from other timesheets, per day.
The totals include unapproved (draft or submitted) time, not just approved time.
Paid time off (PTO) hours logged on a PTO project are reflected in the daily totals.
The other-project totals are read-only in this view.
Mind the Gap
The cross-project timesheet line items grid gains a Review mode that surfaces days where a person logged no time, over a 7 or 14-day window. Reviewers can spot missing time at a glance instead of inferring it from rows that are not there.
Where and How:
Access the 'Overview' O3 module / context menu, selected in the bottom left corner. Then click on the Timesheet menu item and set the grid view to 'Timesheet Line Items'. Then see the button as noted in screen grab adjacent the new quick filters, which by default will say 'Review'. Click on this for time window options.
Example: we see a gap in yellow, indicating a gap:
Details:
For each day in a timesheet period where a crew member or individual user logged no hours, a gap row is shown with that timesheet's header details.
A crew member on two overlapping crew timesheets with no hours on a day shows one gap row per timesheet for that day.
Gap rows are only shown within the selected window and up to today; no gap rows are shown for future days.
A reviewable person with no timesheet covering a past day in the window shows a single unassigned gap row for that day, without timesheet header details.
The selected window (7 or 14 days) is remembered after reloading the page.
While Review is active, the export menu is hidden; turning Review off restores it.
Your Team, Your View
The cross-project timesheet line items grid can now be filtered by Team and by Business Unit, so managers can narrow it to the people they are responsible for. All existing grid actions still work on the filtered result.
Where and How:
From the 'Overview' module, select Timesheets and set the grid view to 'Timesheet Line Items'. The new quick filters are shown on the grid.
Cross Project Overview -> Timesheets -> Quick Filters:
Details:
Selecting a team filters the grid to only that team's line items.
Selecting a business unit filters the grid to only that business unit's line items.
Actions available on the grid continue to work on the filtered result.
Know Your Crew
Employees can now carry Shift Type, Shift, and Employee Status attributes, which populate automatically on timesheet entries and can be overridden per entry without changing the employee record. Two free-text fields were also added to timesheets for ad hoc notes.
Setting your 'Shift' and 'Shift Type' values:
Having setup the lookup values, these can now be adjusted on the Employees (See Employees on Project Settings. Remember to use the padlock button to edit from the grid view!).
Details:
Shift Type, Shift, and Employee Status lookups appear on the Employees grid, save correctly, and can each be left blank.
Shift Type and Employee Status lookup values are project-configurable via the standard lookup mechanism.
When an employee is added to a daily timesheet entry, Shift Type, Shift, Employee Status, and role/position populate automatically from the Employee record.
These values can be edited on the timesheet entry; overwriting a value on the entry does not modify the Employee record.
New Notes and Description free-text fields are available on the timesheet.
Seek and You Shall Find
Timesheets now appear in global search and in the recently visited list, so users can jump straight to one instead of navigating to it. Results respect each user's existing permissions.
Timesheets Located Via Global Search:
Details:
Searching for a timesheet by name returns it in the global search results.
A timesheet the user has opened appears in their recently visited list and links back correctly.
Users only see timesheets they have permission to access in search and recently visited.
Mobile (ONField)
Same View, Anywhere
The crew timesheet column layout is now a project-level setting that ONField mirrors, so field users see the same columns as they do on the web (desktop version).
Where and How:
Open a crew timesheet on the web / desktop and use the column chooser. Project admins are prompted to save the layout to the project.
Details:
All users see the column chooser on a crew timesheet, but only project admins can change it.
An admin toggling a column is prompted to save to the project. Saving makes the layout appear for other users and in ONField; declining does not change what others see.
ONField shows exactly the columns configured for the project, in the same order as the web, on both the line items and crew defaults screens.
Discipline, Company, Shift, Shift Type, and Work Category display correct values in ONField when configured as visible.
Editing a web-entered timesheet in ONField and saving does not clear Discipline, Shift, Shift Type, or Work Category, even when those columns are hidden.
A project with no saved configuration shows the default layout in ONField.
After an admin saves a new layout, ONField reflects it the next time a timesheet is opened online; the last-known layout is used offline.
PIN It Down
ONField no longer saves offline credentials that could never be used, which previously left SSO users stuck at the offline login screen. The offline prompt now asks SSO users for their mobile PIN rather than a password.
Details:
An SSO login with no mobile PIN configured stores nothing for offline use; the next offline login shows no pre-filled username.
An SSO login with a mobile PIN set up allows offline login with the PIN, and the helper text asks for the PIN only.
On a shared device, when a different SSO user without a PIN logs in online, the previous user's stored offline credentials are cleared.
Non-SSO (password) users continue to see the existing "Enter your password or mobile PIN" helper text.
Workface Planning
Right Status, Right Package
Administrators can now define which statuses are available for each IWP Purpose, so package types with different lifecycles only show the statuses that apply to them. Auto-transitions to a status outside the allowed list are skipped.
Where and How:
On the IWP Purpose configuration, use the new 'Allowed Statuses' section.
Project Settings -> Entity Settings -> IWPs -> Purposes tab -> Scroll down to 'Allowed Statuses' section.
Allowed Statuses on that Purpose:
Details:
An admin can save an IWP Purpose with one or more allowed statuses selected.
Users only see the allowed statuses in the status dropdown when allowed statuses are configured on the IWP Purpose.
When the allowed statuses list is empty, all statuses are available (no change to current behavior).
An auto-transition does not fire if the target status is not in the allowed list.
When both allowed statuses and status transitions are configured, the status selector only shows statuses that appear in both lists.
CWP Line Items
What's in a Code?
CWP line items now have optional Code and Description fields, available as columns in the line item grid. These give you a place to carry your own identifiers so O3 data can be reconciled against existing records.
CWP Line Items accessed via the Execution Tasks tab in the form layout.
Note: CWP Line Items can also be accessed via a grid view option, see 'Line Items'.
Details:
Code and Description values can be entered, saved, and edited on a CWP line item, and persist after reload.
Code is limited to 50 characters and Description to 500 characters.
Existing CWP line items are unaffected, with both fields empty.
Bring It All In
CWP line items can now be imported from a spreadsheet, with one file able to span multiple CWPs and handle creates, updates, and deletes.
Details:
A file spanning multiple CWPs imports correctly, with rows landing on the right CWP.
Re-importing an unchanged file produces no duplicate line items.
Changing a value in the file and re-importing updates the existing line item rather than creating a second one.
Rows flagged for delete remove the matching line item; other line items on the same CWP are unaffected.
Invalid rows are handled consistently with other O3 imports.
Drawings
Reading Between the Lines
Drawing data extraction is now available. Using this functionality, O3 can read tags, Bill of Material, and title block information from drawings to augment data within O3.
Creating a Drawing Parser Configuration: Project Settings -> Entity Settings -> Drawings -> 'General Settings tab' -> Drawing Settings -> 'Enable Drawing Extraction'
Creating a Drawing Parser Configuration: Project Settings -> Entity Settings -> Drawings -> 'General Settings tab' -> 'Drawing Parser Configuration'. Click on + to add an entry.
Note: Please reach out to your project manager if you are interested in using this on your project(s).
Hands-Free Extraction
Drawings brought in through an integration can now be extracted automatically, with optional auto-accept and a configurable extraction resolution. Usage limits keep extraction volumes predictable, and a folder Force Refresh backfills drawings on existing projects.
Details:
Parser configuration
Project admins see the 'Enable Drawing Extraction' project setting and the parser configuration grid.
On the rule block, "Pattern Name" is renamed to "Rule Name", and the "Tags" rule family is now labelled "Construction Components".
The help text now explains that matched values are linked to existing Construction Components by Tag Number, falling back to Lookup Key, and otherwise become new Construction Components on accept.
New 'Auto Accept' setting (off by default). When on, a completed extraction is accepted automatically, applying title block field mappings, all Construction Component and BOM rows regardless of confidence, and existing-component linking where enabled on the block.
New 'Extraction Resolution' setting (Standard by default, or High). Automatic extractions always use it; a manual extraction defaults to it, and the user can override it for that run.
BOM parsing: when a quantity has no unit suffix, the configured fallback UOM is used. A unit found in the cell (e.g. "0.4 M") still takes priority.
Automatic extraction
Drawings have a new 'Drawing Parser Configuration' field, visible and editable on the drawing detail.
In the integration folder mapping, a Drawing-type folder can be mapped to a Drawing Parser Configuration.
On sync, new drawings from a mapped folder, and existing drawings with no configuration, receive the folder's configuration. A configuration already set on a drawing is never overwritten.
An extraction is queued automatically when sync creates a drawing or detects a new revision or changed file. Drawings whose current revision already has a Complete or Accepted extraction are not re-extracted.
Force Refresh on an integration folder queues extraction for every drawing that has not yet been extracted for its current revision. This is the backfill path for existing projects.
Where a BIM 360 / ACC drawing has no file in O3, the source file is downloaded, attached to the drawing, and then extracted automatically.
Manual Extract / Re-run on an existing drawing is always allowed, subject to the usage allowance.
Rules and limits
Automatic extraction only runs for projects with 'Enable Drawing Extraction' turned on. Folder mapping still assigns configurations so the project can be backfilled with Force Refresh once the setting is enabled.
Only integration sync triggers automatic extraction; manual attachment upload and CSV/Excel drawing import do not.
Only PDF source files are extracted.
A limited number of extractions run at the same time; additional extractions wait in the queue.
Extraction is subject to a rolling 30-day usage allowance, with high-resolution pages counting more towards it. Once the allowance is reached, manual runs show an allowance-exceeded error, automatic runs are skipped, and an in-app notification is raised. Extraction resumes as the window rolls forward.
In Sync With the Plan
A new project setting keeps a drawing's Planned Start and Planned Finish dates in sync with the planned dates of the boards it sits on. Dates update as boards are re-planned and clear when the drawing is removed from all boards.
Where and How:
The setting is located via Project Setup -> Project Settings -> Entity Settings -> Drawings. Click on General Settings tab (if not already shown by default), go to the 'Drawing Settings' section where you will see the 'Sync Planned Dates from Team Boards' option. Tick the checkbox to enable.
Details:
With the setting off, board activity never modifies drawing planned dates (current behavior unchanged).
With the setting on, assigning a drawing to a board sets its Planned Start/Finish to that board's planned dates.
Changing a board's planned dates updates the planned dates on the drawings assigned to it.
Existing drawing planned dates are overwritten by board dates once one of these actions occurs.
A drawing on two or more boards shows the earliest start and latest finish across those boards.
Turning the setting on does not retroactively change drawings already on boards until the next board assignment or date change.
Removing a drawing from all boards clears its planned dates.
The setting is configured independently per project.
Team Boards and Dashboards
Burning Down, Entity Style
Burndown charts are now available on entity team boards, with a toggle between count and hours. The Team Board Progress widget can also be pointed at any team board, including entity boards.
Where and How:
Open a Team Board. Click on the current view mode (for example Card View or List View) and select the 'Reports View' option.
From an entity Team Board, select the Reports View:
Example Burn Down Chart then Presented:
Details:
Selecting the Reports view on an entity team board displays the burndown chart measuring entities.
Entities reaching a complete status lower the actual line; entities leaving a complete status raise it back.
The unit toggle offers count and hours, and both recalculate the chart.
The unit selection is remembered after navigating away and returning to the board.
Sprint dates, non-working days, and the guide line behave the same as on task-based team board burndown charts.
Color Me On-Brand
Dashboard widgets now support custom text colors, including presets drawn from the O3 brand palette. Selections are saved with the dashboard and carry through wherever it renders, including exports.
Dashboard Widget -> Custom Text Widget -> Pallet Selection:
Details:
Apply an O3 brand preset text color to a widget, or set a custom hex color.
Styling persists after save and reload, and appears everywhere the dashboard renders.
Exported and printed output matches the on-screen colors.
Object Relations
One Rule, Many Types
A single Object Relation rule can now apply to several From Object Types, and rules can be given a name. This removes the need for near-duplicate rules and makes the rule list easier to search and maintain.
Details:
A rule with multiple From Object Types produces the same relations as the equivalent set of single-type rules.
Existing rules have been migrated and behave exactly as before.
A rule must have at least one From Object Type to be saved.
The rule list filter finds rules by Name and by From Object Type name.
Configuration export and import retain multi-From-Type rules and their Names.
Integrations
Custom Entities, Documented
The O3 API documentation now covers User-Defined Entity endpoints, so teams can find and use them when integrating custom entity data with other systems.
Where and How:
The API documentation can be accessed via the Profile button and clicking on the 'API documentation' menu item.
Details:
List and export operations for User-Defined Entities appear in the API documentation and match the actual API behavior.
The documentation follows the same style and structure as the existing standard-entity endpoints.
Each endpoint's parameters, responses, and error cases are documented and can be tested from the API documentation page.
Model
A New Lens
The Autodesk model viewer has been upgraded to the latest v7 release, bringing in current fixes and improvements to model loading and navigation.
Details:
Existing viewer functionality (model loading, navigation, and markups/extensions in use) works as before.
Tags That Stick
Model objects that arrive without a source GUID now receive a stable identifier derived from their geometry, so they can be matched across model revisions. Manual Construction Component tags on those objects survive a model refresh instead of disappearing.
Details:
Re-extracting an unchanged model revision produces identical geometry IDs for every object.
Manually tagged Construction Components on objects without a source GUID remain tagged after a model refresh with unchanged geometry.
An object whose geometry or position changed between revisions receives a new ID, and its tag is not carried over.
Identical objects at the same position receive distinct IDs; identical objects at different positions receive different IDs.
Objects with a source GUID keep it as their primary identifier and also have the geometry ID populated.
The properties panel displays the geometry ID, distinguishable from a source GUID.
Bigger Models, No Problem
Resolves problems encountered when optimizing very large models, improving the reliability of model processing at scale.