Ensure you have the correct version running!
If you don't see 26.17 in the bottom left corner, please clear your browser cache.
What's New - Table Of Contents
Onboarding & Resource Center
I Need a Guide!
O3 adds a help menu dropdown offering quick access to the Help Center and Guided Tours, etc. via the new O3 Resource Center. Users can now find support and walkthroughs more easily from within the app.
In addition, new users are assisted with automatically presented onboarding tours, such as to explain the basic navigation and packaging approaches.
How To:
The O3 Resource Center can be found via the (?) button at the top of the screen.
You can still access the Help Center (which used to automatically launch) as a menu item, or access the O3 Resource Center via the Guided Tours menu option.
On clicking 'Guided Tours,' the O3 Resource Center will then open. The presented menu items here are dynamic and subject to ongoing additions and changes.
How To Guides and Product Tours will be relevant to where you are in the O3 platform. Additional tours will be provided in the future, so watch this space.
Team Boards & Reporting
Power To Procurement
We have now added an option to report out PWP (Procurement Work Packages).
How To:
Go to Project Settings, Report Templates and add via the Templates tab, or for a guide on available template fields etc. Click on the 'Template Fields' tab.
As a recap, use Word to create your template and upload it to O3 so it an auto populate the template based on the fields added to the template document.
Sort Smarter, Not Harder
Lets users reorder tasks within a section on a team board through an import. This makes it easier to maintain the desired task sequence at scale.
How To:
Before:
In this example, we want to reorder the tasks in reverse sort order (bulk update).
We need to create a 'Tasks' Import File.
One option is to change your team board view to Grid View, click on Action button, and then select Export to Excel. However, ensure that you have the required columns are in your grid for the import to work correctly.
So include 'Name', 'Team Board', 'Team Board Section' and 'Team Board Sort Order'.
You can remove any columns that are not needed from your grid in the export file.
You can also use the 'Data Requirements' - 'Tasks' create template option, however the first option will provide the existing tasks names to sort on.
To reorder, use the the 'Team Board Sort Order' column and change the order as suits priority / requirements.
Importing File:
Go to the Imports section.
Add a new import by clicking on '+' button at top right of the Imports grid. Select your file (you may have to save an close the file first!).
Ensure the import type is 'Tasks' and then click on 'Begin Import'. If you are not intending to add any tasks, it is recommended to click on the 'Update Only' option to ensure none are added before beginning the import.
After:
After the Task import, in this example we have reversed the sort order.
I Have No Filter - Oh Yes I Do
Users can now filter entity team boards by drawing type and by the assignee of an open action. This makes it easier to focus on the specific work and people relevant to a board.
How To:
On your Team Board, locate the filter button on the top right and when building your filter, you now have the option to add the 'Open Action Assignees' and 'Drawing Type.'
Example 'Open Action Assignees' filter applied.
Showing a filter has been applied.
Workflows & Status
Let's Reopen the Case
We have added an auto created Approval option, whereby reopening an approval now keeps the originally assigned user when an entity returns to a status, such as after a rejection. This avoids losing assignment context during rework.
How To:
The 'Reopen if entity returns to status' can be found by auto adding an auto created Approval on a status. You will need permission to edit the entity status, via Project Settings, Entity Settings.
When you setup the Approval, the option 'Reopen if entity returns to status' is visible.
Click on the option to activate it for the approval.
Scenario:
Someone approves the approval 'Tech Approval' at the 'Technical Review' status. This then then auto moves the entity/package to a 'PM Approval' status and like namesake approval created. The PM is not happy and decides to Reject their approval.
This approval is setup to move the entity/package back to the 'Technical Review' status on Rejection, and now with the option enabled, the previously approved 'Tech Review' approval is moved from an 'Approved' status back to an 'Open' status, providing an opportunity to address the PM concerns and reapprove when happy to resubmit to the PM.
This option negates the need to delete the 'Tech Review' approval before Rejecting and moving the entity back to the status the approval was created at to recreate the approval. Also this ensures that the approval maintains any updates by recycling the old approval.
Notes:
With the config enabled, returning the parent entity to the status (including via rejection) reopens the approval and maintains the entity's status.
The reopened entity is reassigned to its immediately previous assignee.
The affected user receives a notification per existing notification settings.
Behavior works across multiple approval-enabled entity types.
With the option disabled, existing behavior is unchanged.
I Have a New Role
You can now restrict status editing to a configurable project role (previously just Project admin).
This can provide flexibility where you have non project admins that should be able to still modify the entity at a particular status, such as a Super User, or say you have reached a status where someone on the Quality Team (having say Quality role) can still edit it. For example, to add some specific notes or approval to close out the workflow.
How To:
You will need permissions to go into the Project Settings - Entity Settings - Statuses.
Open a Status to edit the Restrictions section where the 'Require Role to Edit' is shown. Click this and then select the Role.
Note:
The 'Locked Fields' will still be applied, so i.e. if Revision is locked, the editing role cannot edit this field!
Ai Assistant
What's Been Assigned to Me?
Lets users view the actions assigned to them through the AI assistant. This provides a single, conversational place to see what needs their attention.
Why:
Users previously had to navigate to list views to find the actions on their plate. This improvement lets users retrieve and understand their actions conversationally through the AI assistant, so they can quickly see what needs attention without hunting through screens.
How To:
You can click on the Ai Assistant button and either type in your action related question, or conveniently use one of the pre-prepared questions to choose from,
such as 'What actions do I need to work on this week?' or 'What actions are overdue?'
(zoomed in)
Example: What actions do I need to do this week?
Can also include approvals. You can use the hyperlinks to jump to the parent entity.
The assistant can also provide you a summary.
See next improvement below 'Action!' for progressing the actions...
Action!
Allows users to complete specific actions assigned to them directly through the AI assistant. This streamlines follow-through on tasks without leaving the assistant experience.
How To:
Here we have the assistant open. Lets say we have used the above pre-pared questions to see what actions are due this week and we want to add some comments to one of the constraints listed and also reassign it to a colleague ...
With AI simply state what you would like it to assist with and natural language.
Note before the Ai makes changes it will check with you to confirm.
If the Ai assistant cannot progress the instruction, it will let you know, such as may not have permissions or the person being assigned the task does not exist.
So in this case, we can only confirm to proceed with adding a comment to the task. Given one or more actions may not be possible, you always have the opportunity to Confirm or Cancel the updates that can be made.
Say for example, if the Ai could not find the person to assign the task to and the comment read such as 'I have reassigned this task to you as you have the ability to progress the task,' given we could not reassign the task, we probably don't want to add the comment, at this time.
Model
This is My Level
Improves the automated piping packaging experience by previewing level mapping with color-coded components before auto-packaging. Users can review and confirm groupings before committing.
How To:
From a 3D model on the right side from Automated Packaging: Pipe Installation - further down the 'Preview Levels' and 'Clear Preview' buttons are located.
You can hover over the legend circle in the list to see what level the color represents.
The list below shows the level starting position components. If the starting component is incorrect for a level, you can click on the 'X' adjacent to the selection and reselect a new starting point by selecting a new (pipe) component from the model.
Notes:
"Preview" button calculates the level mapping using the selected Starting Component Per Level (CCs).
On preview, we apply a distinct color per level to the corresponding components directly in the model viewer.
Preview is only available when 2 or more levels are selected; with fewer than 2 levels the preview action is blocked.
If the selection is invalid, we block the preview until a valid selection is made.
When changing the Starting Components per Level, the colorization reverts.
Behind The Scenes
We have made some improvements to client-side performance when working with objects, reducing lag and making the interface more responsive.
Users will notice faster load and interaction times, especially on larger datasets.
Schedule & Lookahead
Lets Schedule Them Line Items
O3 enables CWP line items (see Track Line Items below) to be created and updated automatically from schedule imports. This reduces manual data entry and keeps line items in sync with the project schedule.
How To:
On a Schedule click on 'Configure Linked Entity Mappings.'
Create a Configuration Rule (+)
Provide a name and set type as 'CWP Line Item' and then enter in your Field Mappings.
After entering in your mapping, click on the 'Save' button.
We have an API for That
Allows admins to create schedules and copy linked entity mappings between them via the API. This speeds up schedule setup and keeps mappings consistent.
New API endpoint in swagger:
/api/schedules/{scheduleID}/clone-linked-entity-mappings
Notes:
Copying to a target with no existing mappings results in the target having all of the source's mappings.
Copying to a target that already has mappings results in a merged set; pre-existing mappings retained, missing ones added, none overwritten.
A failed copy returns an error response rather than partially applying.
User should be able to copy between projects. If any project specific value such as purpose is copied then it must correctly reference the value in the target project.
It's Better Now
We have introduced some improvements to the way the Lookahead works:
We addressed a lookahead issue where the date window jumped backward after saving; the current date scrolling position is now preserved. Users keep their place when saving changes.
Additionally, we added the ability for lookahead users to click and drag bars to move IWP dates without opening the flyout menu. This makes rescheduling faster and more intuitive.
How To:
The IWP Lookahead can be located from the Workface Planning menu, and then select 'IWP Lookahead' option.
Track Line Items
Line By Line
Enables tracking of (contract) line items against CWPs by IWP task type.
This gives clearer visibility into how work packages progress by task category.
How To:
Admins will need to enable the Line Items within the CWP Settings form, via Project Setup, Project Settings, entity settings, CWPs and then 'General Settings' tab and go to CWP Settings.
Remember to Save Changes.
Also you may need to refresh your CWP form layout if you have this open on another tab!
Line Items are accessed via the Execution Tasks.
Click on '+' to add new entry.
Notes:
With the project setting off, no Line Items section appears on any CWP; enabling it reveals the section.
Creating a line item requires selecting an IWP Task Type; task types already used on that CWP cannot be selected again.
Quantity UOM auto-populates from the selected task type.
Engineered Quantity and Engineered Hours equal the summed quantity/hours of component backlog tasks for that CWP + task type.
IWP Actual, Estimated, and Earned Hours match the rolled-up values from matching IWP tasks.
With no matching tasks, all derived roll-up fields render blank rather than 0.
A construction manager can edit a saved line item's user-entered fields; no delete action is available.
All Together
Want to see Line Items across CWPs? There is a new 'Line Items' grid view option.
Want to Import via a schedule ? See Lets Schedule Them Line Items above.
ONField - Mobile Application
Coded Messages
ONField lets mobile users scan a QR code to set the ONField login URL. This simplifies onboarding by removing manual URL entry on devices.
How To:
A camera icon is displayed on the login settings screen.
Tapping the camera icon opens the device camera in QR scanning mode.
When a QR code is successfully scanned, the app shall extract the encoded URL and validate it against a known ONField URL pattern.
If the scanned URL is valid, it shall be automatically saved as the login URL and the settings screen shall close, returning the user to the login screen
If the scanned URL does not match a known ONField URL pattern, an error message shall be displayed and the user shall be able to try scanning again.
If the user cancels or navigates back from the camera view, the camera shall close and the existing login URL shall remain unchanged.
How to Create a QR Code:
You can right click on an O3 page in Microsoft Edge or Google Chrome browser platforms and there is a menu option to 'Create QR Code for this page'. Click on this.
UDETS (User Defined Entity Types) and Plot Plans
The Plot Thickens
We have added UDET association types in plot plans, enabling your user defined types to be overlayed on the plot plans.
Example 'Path of Permits' view to help users track permitting relationships spatially across the plan.
How To:
See Plot Plans under Early Planning menu section and then click on 'Associate Type'. Then click on UDET you want to manage and overlay on a plot plan.