A couple of big enhancements worth mentioning for this 26.15 release include the IWP Sequencing and the Material Management - CWP - soft allocation process features.
O3 Mobile (ONField)
Keep It Simple
When setting up your ONField connection settings, you can now just enter the deployment name only, with the 'https://' prefix and domain suffix (.o3solution.com) omitted (being applied automatically), reducing errors on mobile keyboards.
How To:
Start the O3 ONField Mobile App. Click on the Cog button on the ONField Login in page. See bottom of screen.
On the URL Configuration input box, just enter in the deployment name. This will typically be your organization, but if you are a subcontractor, this maybe your client's company name.
If unsure, contact your O3 Administrator. Further if you already use the desktop version, it will most probably be same URL/web address deployment.
Example: https://MyCompany.o3solution.com/
You just need to enter 'MyCompany' in the ONFIeld URL Configuration inbox. Then click 'Save Configuration.'
Generally, once set you should not need to change this setting, unless you are working on multiple deployments.
A Picture Paints a Thousand Words...
Field users can now attach photos while creating entities such as RFIs, constraints, and punchlist items in ONField, rather than only after the entity is saved.
How To:
There is a new Attachment (paperclip) icon on the add new RFI form. Clicking on this allows you to attach a document or take a photo.
If you are at the bottom of the page, there is an '+ Add' button adjacent the 'Attachments' section header.
Note: The attachment / Photo is saved after the RFI is created (Saved).
Systematic
System/Sub-system auto-population on selection of CC within Punch List Items in ONField are now available and matches existing O3 (web) desktop behavior.
Notes:
Creating a punch item in ONField with a CC that has System/Sub-system set → those fields are auto-populated and remain editable.
Creating a punch item in ONField with a CC that has no System/Sub-system → fields remain blank, no error shown.
Changing the CC on create after fields are populated → System/Sub-system fields do not reset.
Editing an existing punch item in ONField with blank System/Sub-system, then changing CC → fields auto-populate from the new CC.
Editing an existing punch item in ONField with non-blank System/Sub-system, then changing CC → fields are not overwritten.
I'm Connected
ONField now automatically prompts users to sync pending offline data when connectivity is restored, so field users no longer have to remember to trigger a sync manually.
It's Locked
Username field is locked while offline and clarifies that only the user who went offline can log back in, preventing unexpected offline logins by other users.
Timesheets
The Outer Limits
Field users can now select IWPs outside their assigned crew on timesheets, making it easier to log time accurately after mid-shift reassignments or work that crosses IWP boundaries.
How To:
From the timesheet, the 'Other...' option is shown where an IWP present a drop down selection list, such as Default Hours By IWP and on the Resource Hours section grid.
When 'Other' is chosen, you are then presented with the IWP grid list. Click on the IWP to add and click on 'Choose Items' to confirm selection.
Note the initial filter in bottom left for 'Incomplete IWPs Only'. Turn this off if you are adjusting hours spent on completed IWPs.
Notes:
Currently for Desktop version only.
O3 introduces an "Other" option, which is visible on the IWP dropdown on the timesheet.
Selecting "Other" / "Other..." successfully opens the full IWP entity chooser.
The IWP chooser defaults to showing incomplete IWPs only.
A selected IWP is added as a normal timesheet row with no visual distinction from crew-assigned IWPs.
The selected "Other" IWP does not appear in the IWP dropdown on subsequent timesheets.
Sequencing and Scheduling
Crunch Time
We excited to introduce the O3 IWP Sequencing Tool (Available from the IWP Lookahead' menu) with options to sequence with different approaches and sequencing requirements. Let O3 crunch your IWP execution sequence for you!
To Do:
From the Workface Planning menu, select IWP Lookahead. From this grid click on the 'Sequence IWPs' button.
This will put the Lookahead into Sequencing Mode and the grid heading will change to 'Sequencing IWPs'.
To start the process, click on the 'Optimize IWP Sequence' button at the top. If you want to exit this mode, click on the 'Cancel' button next to it.
When optimizing you will have two options, 'Critical Path Method' or the 'O3 Sequencer' approach.
The former CPM approach, O3 will use a straightforward, IWP predecessor to IWP successor logic to sequence the IWPs.
If you use the latter option, you then have some sub options to consider, such as respect crew capacity, prioritization, group by CWP, etc.:
When ready, click on the Optimize button option (or Cancel to abort).
After the Optimize, you will be shown if there are any warnings and confirmation if otherwise successful.
Previous bar positions are shown ghosted (grey) so you can compare / review movement.
Example Ghosted / Previous (Current) bar positions.
To commit the proposed changes, click on the 'Save Changes' button.
Bar Tool Tips shown when hovering over a bar, with reason for sequence placement.
Notes:
With an IWP that has pinned planned dates (with “Keep Planned Dates When Sequencing) and a crew, the process uses the planned dates; removing the dates or the flag falls through to crew productivity → 10-day default.
Will not move pinned IWPs with Actual Start date.
Sequenced non started IWPs will be replanned from current date (i.e. today onwards).
Two CWPs/CWAs with differing planned dates and no hard dependency or Purpose Ordering to sequence them. The earlier-planned work is biased earlier in the result, but a hard dependency or capacity constraint still wins over the soft ordering.
A run sequences IWPs that are not visible/paged in the grid (full-project scope confirmed).
After a run, an IWP whose new dates fall inside the window appears in the Gantt; an IWP moved outside the window remains displayed with its new dates.
On Apply, Planned Start/Finish are persisted for all displayed IWPs with modified dates.
A dependency cycle, an IWP with no resolvable duration, and an IWP with no crew pool each produce a visible warning.
After a run, a staged/moved bar's tooltip includes a "Reason: …" line explaining why it was placed there, and that line disappears once the change is Applied, Cleared, or Reset.
We are interested in your feedback on this new feature.
We Got Your (Project) Number
O3 can now automatically identify which project to import from a multi-project XER (Primavera P6) file.
Notes:
A .XER File Project Name field is available on the O3 schedule entity and can be populated by a Project Manager.
When a multi-project XER is imported (via any method) and the field is populated with a valid project name, the correct project is auto-selected and imported without user intervention.
When a multi-project XER is imported and the field is blank or the name doesn't match, the system falls back to current behavior without erroring unexpectedly.
Single-project XER imports are unaffected by this change.
We Got Better Metrics!
Weekly Work Plan has earned-hours-based PPC (Percent Plan Complete) metric, CWA grouping, and a horizontal scrollbar for smaller screens, improving accuracy and usability for field users.
How To:
Select the week of interest (defaults to current week).
Change the groupings.
This updates the grid view grouping.
To collapse / expand groupings.
Enter your committed hours / quantity (see selector at top) and actual hours / quantity.
Week totals are shown at the bottom of the grid.
What's More!
Users can now manually add off-plan IWPs to the Weekly Work Plan, giving field crews visibility to report against work that falls outside their standard filters (i.e selected week).
How To:
Click on '+Add Off Plan IWP.'
Select the IWP/s you wish to add and then click on the 'Choose Items' button.
Manually added IWPs are identified with a red x adjacent, which can be used to remove them from the week's view if no longer required/worked on in week.
For The Record!
Adds the ability to export the Weekly Work Plan to PDF while preserving conditional formatting, for client submissions and record-keeping.
How To:
In top right, there is an option to export view to PDF.
PDF Output Example:
Material Management
What Happened to My Delivery?
Adds material readiness comparison at the CWP Material Requirement level, so project managers can see whether purchased materials will arrive in time to support the Path of Construction.
How to - Configuration:
Lookup / Priority can be customized as shipments or e.g. Priority 1, 2 3...
See Project Settings - Lookups - select 'Material Priority'.
The priority order will be in order top to bottom in list. You can change the order using the sort button at the bottom, or manually (mouse) drag to position using the 3x3 icon adjacent the value to move.
Then apply this material priority to your CWP.
If the 'Material Priority' is not shown on the form layout, it will need to be added by Project Admin / someone with permission to add to the form layout/s available.
If a priority is not set, the next consideration will be the Planned Start Date (PSD) of the CWP.
How To - CWP Material Ready Status:
The Material Status can be configured via Project Settings - Entity Settings - CWPs - General Settings - Materials Section - Material Ready Status.
Note: a default list will be supplied, but this is configurable with the exception of 'Not Ordered' and 'Insufficient Quantity,' which are required by the system to be present.
Their status color can be modified.
So as an example (see screen grab), we have indicated its Early if PO Line Item is forecast more than 30 days before CWP PSD.
Note: If Days (To/From) left blank, then O3 treats as infinity. So if Early 'Days From' is blank it means any date up to supplied 'Days To' in this case (negative) 30 days forecast before PSD.
Early, for example, is forecasted between Days From of (negative) 29 days before PSD, to on same date (0).
'At Risk' is forecast 1 day after PSD, up to 30 days after PSD, and anything 'Late' is anything over 31 days forecasted after PSD.
Again these are configurable and can be changed to support project requirements.
Tip: ensure the status supplied covers the situations, i.e. be wary of date condition gaps!
How To - Schedule CWP Material Allocation Analysis:
Just above the Material Ready Status banding, you can schedule this Material Allocation analysis to be run, say nightly or for testing / immediate update, you can click on the 'Run Now' button, where necessary permissions allow.
Note: This is not run as an Import / no import history will be shown.
How to - Purchase Orders - Line Item Matching:
Example: Purchase Order and Line items. The PO is not directly tied to the CWP, but the allocation process will look at what is required on the CWPs against the PO Line Items, matching the material category codes. It will check if material is ordered, what the forecast delivery date is and how much has been ordered, consider the material priority and or PSD, to then determine a material status on the CWP for each material.
How to - CWP - Material Soft Allocation Results:
Navigate to Construction Work Packages - Material Requirements (Grid View).
Against the Planned Start Date (PSD), the status can be seen in the 'Material Ready Status'
Processing Notes:
CWP with higher Material Priority sort order receives allocation before a CWP with higher Material Priority sort order when supply is constrained; within the same shipment, earlier PSD (Planned Start Date) wins.
A CWP Material Requirement with no matching PO Line Items displays status "Not Ordered".
A CWP Material Requirement where ordered quantity is less than required displays status "Insufficient Quantity".
A user can define custom date-band statuses in Project Settings; the defaults (Early, On Time, At Risk, Late) are pre-populated but fully editable.
When all material for a requirement is allocated with forecast dates, the Material Ready Date field is populated with the latest forecast arrival date.
The Schedule CWP Material Analysis option appears in Project Settings > Entity Settings > CWPs and functions the same as the IWP equivalent.
Teams and Tasks
New Board!
Adds the ability to create an Entity Team Board so engineers and project managers can track entities (e.g. heat-traced drawings) by lifecycle status rather than by individual tasks, giving a clearer view of where each entity stands.
How To:
From the Project Menu, select Team Boards, then All Team Boards.
From there, click on the '+' to add a new Team Board. For the Board Type (New Feature), select 'Entity.'
To save changes, click on 'Save' button.
Click on the '+' button again and from the menu, and this time select 'Add Entities.'
From the list - select the ones you want to add to your board.
Lets say we selected Drawings. Now choose which Drawings we wan to track on the board (select all or individual ones). When done, click on the 'Choose Items' button at bottom.
Note: in Card view you can group columns for sections or by status.
You can also click on Open Actions button for a quick list of outstanding / open actions like constraints.
Members Only
API Documentation: the global project team members endpoint and adds API and bulk CSV import/edit support, enabling customers to sync project team membership from external systems.
Notes:
Both endpoints have been documented for Swagger: projectteams/{id}/members/list and
projectteams/{id}/members/grid-export appear under "Project Teams."Global teams themselves are discoverable via the already-documented projectteams/list/{projectID} endpoint using 0 as the project ID.
Import logic allows empty project. It also updates the User Account Import so the Project Team lookup no longer requires a project. It matches the project-specific team first and falls back to a same-named global team (ProjectID 0), allowing users to be imported onto global teams.
Path Home
Execution task detail forms now display an Entity Type > Entity Name breadcrumb, so users can see which entity a task belongs to without navigating away.
How To:
For example, if we were to open from the Actions menu, the Execution Tasks,..
opening the task now displays the path / breadcrumb, indicating the parent entity type and entity name (such as Installation Work Package and parent IWP is IWP-002, as example below).
Drawing entity example. You can click on the parent entity hyperlink to go directly to that entity form layout view.
That's History
Progress history now shows previous and changed earned quantity and hours for backdated entries, giving project managers the context to understand the impact of backdated progress.
How To:
Access the IWP Grid. On Grid chooser, select Progress History.
The Previous Earned Quantity and Hour columns are now available.
Notes:
On the grid, a Quantity task progressed multiple times shows Earned Quantity and Previous Earned Quantity/Hours reflecting the prior entry.
A Step-Completion task with partial progress shows Previous Earned Hours from that step's prior entry (16h to 32h shows previous 16), and Earned Quantity once Total Units is set.
Each step's "previous" reflects that step's own prior entry, not another step's.
Existing columns (Value, Earned Hours, dates) and unaffected records continue to display correctly.
Back In Time
Admins can now import work package execution progress with backdated Date earned values and correct dates on existing progress records, helping reconcile historical progress data.
How To:
To import, use Work Package Execution Tasks import with a "Date earned". See notes below for further details.
Changes Made:
Notes:
C1: Running a WP Execution Tasks import with a "Date earned" column sets the earned date to the specified past date on the imported tasks.
C2: Running a WP Execution Tasks import without a "Date earned" column defaults the earned date to today.
C3: Running a WP Execution Task Steps import behaves the same as C1 and C2 for the "Date earned" column.
C4: Running the progress history import by package lookup values successfully updates the "Date earned" on existing records.
C5: Running the progress history import by ID successfully updates the "Date earned" on existing records.
C6: Attempting to update fields other than "Date earned" via the progress history import has no effect (or is not supported).
C7: A row in the progress history import that does not match an existing record returns an error.
C8: Verify progress change history gets created after progress history update import.
Reporting
Now That Code Makes Sense
CWA Description is now available as a configurable field on RFIs and UDETs, so it can be shown in grids, reports, and form layouts for reporting and tracking.
Who Dunit?
Report templates now support #CompletedByUserEmail# and #RejectedByUserEmail# placeholders in the approval table, letting project managers surface approver email addresses in generated reports.
These are shown from the Report Templates - Template Fields tab. Navigate to sub tables and select approvals. Scroll down and the two new entries are listed.
Example Report Template usage:
Other
Saved By The Bell
Users are now warned with a confirmation dialog when navigating away from a detail form that has unsaved changes, preventing accidental data loss.
It's All In The Name
We have added a short code field to the Interface Point Type lookup, that is available as a mask token, so admins can build type-code-based naming patterns for interface points.
How To:
What's The Point Interface?
O3 is introducing an Interface Point Category lookup, allowing users to classify and filter interface points (e.g. Soft, Hard, Engineering, Pre-comm) for better reporting and organization.
How To:
Just My Type
We have added 'Contract Type' and 'Administering Organization' fields to the Contracts entity, so project managers can track this information directly in O3 and improve reporting and data completeness.