Ensure you have the correct version running!
If you don't see 26.13 in the bottom left corner, please clear your browser cache.
What's New - Table Of Contents
What's Left?
IWP Lookahead now distributes remaining hours across future dates only.It's All In The Details
Planners can now open a right-hand flyout panel directly from the lookahead Gantt chart by clicking on any IWP bar.The Whole Picture
PDF Gantt exports from the IWP Lookahead now include distributed hours.I Can Relate To That
Double-click dependency arrow on Gantt charts to open relationship edit form.
Keep It Real - Time
Can now specify date progress was earned vs. progress entered date.There is a Task For That - Drawing
Ability to auto-create drawing execution tasks that match configurable attribute filters upon import.
Now That's Convenience
Quality Form templates can now create new lookup types and edit existing lookup values directly within the form builder.
I Love History
A Status History bar has been added to the TWP Details page.Sky's The Limit
New TWP Skyline and TWP Status Skyline widgets for reporting TWPs.Systems Are Go!
System and Sub-system fields now auto-populate from selected Construction Component's attributes.
Yes - You Can Do That On The App
ONField now supports multiple SSO identity providers on a single deployment.
What's the Evidence?
Two new text fields — Evidence Required and Evidence Provided — have been added to all UDET (User Defined Entity Type).
Schedule, Dates and Lookahead
What's Left?
The IWP Lookahead now distributes remaining hours for in-progress IWPs across future scheduled dates only, eliminating misleading workload data on past dates so project managers see a more accurate forward-looking schedule.
How to Do:
Ensure the 'Remaining' hours option is enabled.
For bars otherwise in past (not completed) with remaining hours, these will be shown as totals after time now line (red dotted line).
It's All In The Details
Planners can now open a right-hand flyout panel directly from the lookahead Gantt chart by clicking on any IWP bar, allowing them to view and edit IWP details, schedule fields, and dependency information without leaving the chart. Dependencies can be added, edited, or deleted from the flyout, with all changes saved explicitly via a Save button.
How To Do:
Click on a bar for the details on the right. Make any changes, like dates, crew and dependencies and then click on Save or otherwise click on the 'X' button in top right top to close the panel.
The Whole Picture
PDF Gantt exports from the IWP Lookahead now include distributed hours for each IWP in their corresponding date columns, matching the on-screen view and giving project managers a complete workload picture when working outside the application.
How To Do:
Click on the download button and select 'Export to PDF'.
Example PDF output showing distributed hours:
I Can Relate To That
Project managers can now double-click any dependency arrow on Gantt charts to open the relationship edit modal pre-populated with current relationship details, allowing them to change the relationship type and lag/lead time directly from the chart without navigating away.
How to Do:
Example: Select a Gantt chart such as on 'IWP Lookahead'. Ensure that the 'Dependencies' (see button) is switched on to show the relationships between bars (e.g. IWP packages). Now double click on a relationship line between two bars to open the 'Association Details' form.
From here you can change relationship types and lag.
Tasks and Progress Measurement
Keep It Real - Time
Users with the appropriate permission can now specify the date on which progress was earned when entering IWP execution task progress, rather than defaulting to today's entry date. This ensures progress curves and lookahead reporting reflect the actual construction timeline rather than when data was entered.
How To Do:
First 'Enable Backdating Progress', which can be located from Project Settings, Entity Settings, IWPs, and then click on 'General Settings' tab and 'IWP Settings' sub section.
System Admins establish Role/s with permission to backdate progress.
When completing task you can enter the date the progress is earned.
You can use the 'Progress Timeline' section to locate an existing entry to edit (see pencil button to right) and enter the date earned.
Application:
Also applicable to partial progress and...
...progress by quantity:
Bulk Progress updates:
There is an earned date at the top of the 'Execution Tasks Progress' section.
Select the date the progress is being earned, and then update the entries by row and by column (which will record that earned date entered).
Reporting:
There is now a new IWP 'Progress History' grid view option (note the 'Progress Change History' option is still available and is based on the 'Change History' data, as different to earned progress taken dates).
This shows the date earned, but also indicates date modified, etc. dates as well.
IWP Progress Curve Chart:
If you edit the chart widget, you now have an option to select the Earned Hours Basis.
Options include Progress Entered Date, Step Completion Date and Date Earned.
There is a Task For That - Drawing
Project settings now include an auto-create option per drawing execution task type, allowing the system to automatically generate execution tasks for drawings that match configurable attribute filters upon import, reducing manual setup time and the risk of missed tasks.
How To Do:
Within Project settings, locate Entity Settings and then Drawings. Then select the 'Execution Task Types' and then from the list. Either add ('+') or edit an existing entry.
With the edit/add form layout open, locate the 'Auto Create' option and tick to enable.
Once enabled you can access the 'Auto Created Execution Task Items section and either add or edit.
Adding a new task, define the name of the task and default values as appropriate,
such as Total Units, Earned Hours and also task assignments.
Note: You can also apply a filter so the task is only created if the criteria is met.
The filter will use the Drawing fields such as CWA, Drawing Type, Drawing Name, Revision Number, Revision date, etc.
For example, having imported or manually added a drawing with Number that matched the filter criteria (e.g. contains 'Task'), the execution task is now created.
Quality Forms
Now That's Convenience
Users building Quality Form templates can now create new lookup types and edit existing lookup values directly within the form builder, eliminating the need to navigate away to the lookup management area and then return to the form.
How To Do:
From Project Settings, select 'Quality Forms'. Then select 'Quality Form Templates'.
Either add a new template or edit an existing one.
Under 'Form Fields' you can add '+ Add Field' and set the field to 'Lookup' or locate an existing field that shows ' Lookup' as the Field Type.
To create a new list click on the '+ New' button.
Give the Lookup List a name, and add the value list items to it. When done click 'Save List'.
You can as before review and manage lookup lists from the 'Lookup Lists', tab, however the steps noted above means you don't have to switch to this tab while setting up new form fields for your Quality Form Template.
Testing and Punch Items
I Love History
A Status History bar has been added to the TWP Details page, matching the existing IWP Details implementation and giving users a full view of how a TWP's status has changed over time, including timestamps and the user who made each change.
How To Do:
To add status history to the TWP form layout, a Project admin needs to edit the form layout and add ('+Add Field') the 'Status History' feature to the form.
Sky's The Limit
A new TWP Skyline widget is now available on dashboards, providing project managers with a timeline visualization of TWP plans equivalent to the existing IWP Skyline widget. A TWP Status Skyline widget has also been added to support status-based reporting for TWPs.
How To Do:
Create a new or edit existing Dashboard (see under Dashboards).
From the Dashboard, click on the add widgets and on the search locate the TWP Skyline and TWP Status Skyline widgets. For example, use the search widget to locate.
On selecting / clicking on the entry, the widget is added. you can resize and move as required.
Systems Are Go!
When creating or editing a punch item, the System and Sub-system fields now auto-populate with values from the selected Construction Component's attributes, reducing redundant data entry and minimizing errors for all clients using the punch item module.
How To Do:
Add or edit a Punchlist Item (can be edited from an entity setup for Punchlist or otherwise access grid under the Action Management project menu).
From add or Edit Form layout, locate the Construction Component input and click on selection button ('...').
From the list, select the Construction Component that the Punchlist Item is connected with. If this has a System / Sub System noted this will be copied across to the Punchlist Item
Example of System allocation copied to the Punchlist Item.
Mobile - ONField
Yes - You Can Do That On The App
ONField now supports multiple SSO identity providers on a single deployment, allowing users from different organizations, such as owners and contractors, to each authenticate through their own configured IdP by selecting their organization at the login screen.
If you click on the '>' button adjacent the 'Signing is as', you then get to choose other available login options.
Note: If your account is not SSO (Single Sign On), you will need to enter your O3 user name and password.
Miscellaneous
What's the Evidence?
Two new text fields, 'Evidence Required' and 'Evidence Provided', have been added to all UDET (User Defined Entity Type). Enabling teams to capture and track evidence documentation requirements and status directly on UDET records.
For example, you may have a UDET defined as an NCR (Non Conformance Report) and you are using these fields to support evidence gathering.
If needed on the form layout, have your Project Admin modify the form layout and add the fields on the form where required.
The evidence fields are both rich text type format. More detailed evidence could be supplemented as attachments.
END