Skip to main content

Guide - The IWP Progress Curve Chart

A guide to the 'IWP Progress Curve' dashboard widget

Written by Roy Abery

Overview

The IWP Progress Curve is a dashboard widget that plots planned vs. actual progress over time for a set of Installation Work Packages (IWPs). It is the classic construction “S-curve”: a combination chart that overlays period-by-period activity (vertical bars) with cumulative running totals (smooth curves), letting you see at a glance whether work is tracking ahead of, on, or behind plan.


The chart can measure progress in hours (the default) or in quantity (units of measure), and it can be grouped by day, week, month, or year.

What The Chart Shows

The chart uses two value axes:

  • Left axis – Bars (per-period values): how much was estimated, earned, or actually worked during each individual period.

  • Right axis – Curves (cumulative totals): the running total from the start of the chart through each period. These are the S-curves.

You can turn each series on or off independently:

Series

Type

Meaning

Estimated

Bar

Planned hours/quantity scheduled to be completed in that period

Earned

Bar

Hours/quantity credited as complete in that period

Developed

Bar (optional)

Planned development progress, weighted by each IWP’s % developed

Actual Hours

Bar (optional, IWP only)

Hours actually charged to the IWP from approved timesheets

Cumulative Estimated

Curve

Running total of planned progress — the planned S-curve

Cumulative Earned

Curve

Running total of earned progress — the actual/earned S-curve

Cumulative Actual Hours

Curve (optional, IWP only)

Running total of timesheet hours charged

Reading the chart: where the Cumulative Earned curve sits relative to the Cumulative Estimated curve tells you schedule performance — above the planned curve means ahead of plan, below means behind. The Cumulative Actual Hours curve compared against earned shows productivity (are we burning more hours than we’re earning?).
​

How The Numbers Are Calculated

The chart is built from the IWPs that match the dashboard’s filters. For each reporting period (e.g., each week), the system computes a cumulative value for each series, and the per-period bars are simply the difference between one period’s cumulative total and the previous one.

Estimated / Planned curve

Planned progress is spread across each IWP’s scheduled duration using straight-line (linear) interpolation. For every IWP, at the end of each period:

  • If the period end is on or after the IWP’s finish date → the IWP contributes 100% of its estimated hours.

  • If the period end falls within the IWP’s scheduled window → it contributes a proportional share:

    • Estimated Hours × (days elapsed from start to period end ÷ total scheduled duration)

  • If the IWP hasn’t started yet → it contributes nothing.

These partial values are summed across all IWPs in scope to produce the cumulative planned curve. The schedule dates used are controlled by the Group By Date setting (Planned or Forecast).
​

Earned curve

Earned progress reflects work actually credited as complete. There are two calculation bases (set by Earned Hours Basis):

  • Progress Entered Date (default): Uses the progress history recorded against each IWP. For each period, it takes the most recent earned-hours entry for each IWP dated before the period end, and sums them. This reflects when progress was recorded in the system.

  • Step Completion Date: Sums the earned hours of each individual execution step that was marked complete (and not excluded) before the period end. This reflects when the work was actually finished, which can differ from when it was entered.

Actual Hours (IWP only)

Actual hours come exclusively from approved timesheets charged to the IWP. Hours from un-approved timesheets are not counted. Hours are attributed to the day they were worked (with special half-credit handling when the chart is grouped in half-day intervals).

Quantity mode

When the chart’s value is set to Quantity instead of Hours, earned and estimated values are weighted by each IWP’s key quantity relative to its estimated hours, so the curve reflects installed units rather than labor hours. (Actual Hours is not available in Quantity mode.)

Settings Reference

Setting

Default

Description

Value

Hours

Measure progress in Hours or Quantity

Reporting Time Interval

Week

Period grouping: Half-Day, Day, Week, Month, or Year

Intervals Previous

6

Number of past periods to show (max 18 for week/month/year, 30 for day/half-day)

Intervals Future

6

Number of future periods to project (max 30)

Show Estimated / Estimated Cumulative

On

Planned bars and planned S-curve

Show Earned / Earned Cumulative

On

Earned bars and earned S-curve

Show Development

Off

Adds a planned-development bar series

Show Actual / Actual Cumulative

Off

Timesheet-based actual hours (IWP only)

Group By Date

Planned

Use Planned or Forecast schedule dates for the estimated curve

Earned Hours Basis

Progress Entered Date

Whether earned values follow entry date or step completion date

Show Cumulative Hours as % of Target

Off

Plots cumulative curves as a percentage of a target value instead of raw hours

Target Hours

0

The target used for the % calculation above

Start with Project Cumulative Hours

Off

Starts cumulative totals from the project’s full history rather than resetting at the first visible period

Shift Start

0:00

Time of day the working day/shift begins (affects period boundaries)

Reporting Cutoff Offset Minutes

0

Fine-tunes the daily reporting cutoff for half-day reporting

The chart also honors the project’s time zone and reporting cutoff hour, so period boundaries align with the project’s local working calendar.

Required Fields

An IWP must have both a start and finish date for the selected schedule type (Planned or Forecast) to appear on the chart at all. IWPs missing either date are excluded from the dataset entirely — they contribute to none of the series (estimated, earned, or actual hours), even if they have recorded progress or charged timesheet hours. Beyond that baseline requirement, each series needs:

  • Planned S-curve: Estimated Hours on each IWP (for Quantity mode, a Key Quantity greater than zero is also required).

  • Earned S-curve: Recorded progress history (earned-hours entries) on the IWP, or completed execution steps with earned hours — depending on the Earned Hours Basis selected.

  • Actual Hours: Approved timesheet entries charged to the IWP.

Practical Notes

  • Progress is rolled up from the bottom: execution steps carry weights, and an IWP’s percent complete and earned hours are derived from the weighted completion of its steps. The curve reflects those rolled-up earned values.

  • Because the estimated curve uses straight-line interpolation, it assumes work is planned to accrue evenly across each IWP’s duration; it does not follow a manually entered planned distribution.

  • The earned curve is “as-of” accurate — it always reflects the latest known earned value for each IWP up to each period, so historical periods stay consistent with the most current progress data.


Did this answer your question?