Skip to main content

Release Notes 26.10

Released May 13th 2026.

Written by Roy Abery

Ensure you have the correct version running!
If you don't see 26.10 in the bottom left corner, please clear your browser cache.
​​


What's New - Table Of Contents

  • Into Reports?
    A new Template Fields reference tab has been added under Project Settings > Report Templates, giving users a convenient reference to available fields when building or editing report templates.

  • Skies The Limit
    Users can now view detailed reporting on IWP and CWP status, providing better visibility into work package progress and completion rates across the project.

  • Totally Automatic
    The system now automatically determines the Schedule name reference from the source filename when importing a Schedule Activity dataset, reducing setup steps and speeding up the import process.

  • Do You Speak My Language?
    A new System Admin screen has been added to configure which languages are enabled in the platform, giving administrators control over multilingual support settings.

  • What's the Risk?
    The Risk Log now includes CWA and Monte Carlo Risk fields, enabling richer risk analysis and better alignment between risk data and construction work areas.

  • No Data Left Behind
    Administrators can now propagate task type changes to existing execution tasks, ensuring consistency across task records without requiring manual updates to each individual task.

  • We Deliver on Quality
    Quality Forms can now be associated as deliverables on IWPs, TWPs, and Systems, enabling formal quality documentation to be tracked alongside construction work packages.

  • API Swagger documentation now displays entity column lists as sample responses, making it easier for developers and integrators to understand available data fields at a glance.

  • Users can now manually export IWP bounding boxes from the model, enabling offline use and integration with external systems that require spatial data.

    • In Scope: We Added Scope Start Date and Scope Finish Date fields to CWPs.

    • Straight To the Point: Click on a data diagram node to navigate to the linked data deliverable.

    • We Got You Systems: We added additional Dashboard Widgets for Systems Entity.

    • Lets Be Direct: Manpower resources on work packages can now be classified as direct or indirect, enabling more accurate resource planning and cost reporting for project teams.

    • Optimized: We optimized the SyncAttributes process for models with thousands of attributes, significantly reducing sync times and improving performance for large-scale projects.

    • It's A Date! Date fields for Baseline, Forecast, Early and Late, added for Construction Work Areas, enabling more precise scheduling and tracking of CWA timelines.

    • Doesn't Time Fly? A 'Next 6 Weeks' time filter option has been added to all Gantt views, making it easier to focus on near-term work and upcoming project activities.

    • Moving On! A right-click context menu option is now available to move tasks between sections on the Task Board, streamlining task management and improving workflow organization.

    • Lets Make A Group: Users can now group the Project Gantt view by Construction Work Package, making it easier to visualize and manage work organized by package.

    • I Need My Space: Users can now collapse the left-side navigation menu on both the Project Gantt and Gantt views, providing more screen space for reviewing and managing project schedules.

    • You're Special: Schedule imports now correctly handle date fields containing special characters, preventing import failures and ensuring all schedule data is captured accurately.

    • Things Are Looking Up: Scaffolding can now be created directly from a scaffold request, with the association automatically reflected through a status update, streamlining the scaffold lifecycle process.

    • Going Automatic: The PWP number is now automatically populated on the Construction Components table after a graphical PWP assignment is made, reducing manual data entry and keeping records consistent.

    • I Need More Power - You Got It: Project Admins can now edit dates, dependencies, and shift successors directly within the scheduling tool, giving them greater control over project timelines without needing elevated system access.

    • If This 4D Gets Any Better It will be 5D: The 4D simulation player now supports Baseline, Early Start, and Late Start date options, giving users greater flexibility in visualizing project sequencing scenarios.

    • Tell Me Later: Rather than waiting on multiple / large exports to take place, you now have the option to be notified by email or via an in-app popup message when the export is completed.

    • You've Got Mail!
      We expanded the User Account Email History - to show not only the last event for that email, but all events (including when the initial email was sent - event!)


Into Reports?

A new Template Fields reference tab has been added under Project Settings > Report Templates, giving users a convenient reference to available fields when building or editing report templates.
​
​How To:

This is available to Admins / Project Admins and those with permission to create reports. You can use the report templates to create your Work Package report, RFI tracking sheet, Weather Report, etc.
​
The report templates are located via Project Set-up, Project Settings, Report Templates. For further information on Report Templates, click here for the guide.
​
Then click on the 'Template Fields' tab. Select the Report Template Type (this could be a user defined type, say to track NCRs or Changes) or typically IWP and CWP reports types, but other types are available also.
​
Ideally you would be generating your report template in Word alongside this and use the convenient 'Copy' field name option adjacent the field you want and paste into your Word template, where you want to show the field value from O3. Further there is also a Filter option near the top to more easily locate fields of interest.​


Skies The Limit

Users can now view detailed reporting on e.g. IWP and CWP status, providing better visibility into work package progress and completion rates across the project.


​How To:
In a reporting dashboard, click on add widget (+) and search for 'Status Skyline' to see a list like below. Select the appropriate one you wish to add to the dashboard.
​

Example IWP Status Skyline Report:


Click on the widget settings to change date field basis, grouping, time interval, period and title.


Totally Automatic

The system now automatically determines the Schedule name reference from the source filename when importing a Schedule Activity dataset, reducing setup (config) steps and speeding up the import process.
​
​Addressed Scenario: When importing a Schedule Activity data deliverable, if the CSV does not contain a schedule name column, users had to manually add a configuration rule to inject the schedule name before the import could run.
​​

Process: When a Schedule Activity data deliverable is imported and no schedule name is resolved from the CSV column or any configuration rule, O3 will derive the schedule name from the uploaded file's base filename with the extension stripped (e.g., Q2-Schedule.csv = Q2-Schedule).


Do You Speak My Language?

A new System Admin screen has been added to configure which languages are enabled in the platform, giving administrators control over multilingual support settings.
​
​How To:
First you will need to be a System Admin in O3. From the System Admin context menu, select System and then Language Support.
​

Then check the languages you want the O3 deployment to make available to the login screen, project, and menu. Languages will then be available to the language picker in the user profile.
​
​Note: (Auto Generated) refers to language support that is generated from computer system translations. Some languages (where this is not shown) have been manually refined by O3 to improve AWP / construction context for clearer explanation.
​


What's the Risk?

The Risk Log now includes CWA and Monte Carlo Risk fields, enabling richer risk analysis and better alignment between risk data and construction work areas.

O3 has added the following fields to the Risk Log:
​

  1. Impacted CWAs — multi-select, populated from the project's CWA list

  2. Probability Percent — percentage input (0-100) - whole numbers only (not fractions of a percent)

  3. ​Minimum Projected Impact (days) — integer, accepts positive and negative values

  4. Average Projected Impact (days) — integer, accepts positive and negative values

  5. ​Maximum Projected Impact (days) — integer, accepts positive and negative values


All five fields are non-default and must be added to the detail form by a project administrator via form layout configuration if they wish to use.


No Data Left Behind


Administrators can now propagate task type changes to existing execution tasks, ensuring consistency across task records without requiring manual updates to each individual task.
​
​How To:
​
Navigate to Project Setup - Project Settings - Entity Settings (e.g. IWP), Execution Task Types (assuming changes to the Execution type have occurred after already being used on work packages, such as a change to rate of placement from 1 to 1.2). Select the type to sync (example below - 'Concrete').

From the Action menu, select “Update Existing Tasks with Current Configuration.” Then after the menu selection, you will be presented options to what historical data you wish to sync. Other options include only un-started tasks, or all which can impact in progress and completed task progress. Click Apply button to proceed.


We Deliver on Quality

Quality Forms can now be associated as deliverables on IWPs, TWPs, and Systems, enabling formal quality documentation to be tracked alongside construction work packages.
​
​How To Do:
​
​Set-up (Permissions required): Quality Form Templates can be accessed via Project Setup by navigating to Project Settings - Quality Forms - Quality Form Templates (tab). If none shown - click on '+' button to add one.

Double left click on one of the templates of interest. Scroll down to Entity Associations and click on which ones will be applicable, such as IWP, TWP or Systems.
​

Save Template if any changes were made.

Using Quality Templates: For example (IWP), open an IWP and navigate to the 'Deliverables' tab. Click on the '+' button and select 'Quality Forms' from the list.
​


Select the Template you wish to use (if not shown, check settings noted above).
​


This is now added and can be populated accordingly.


That API Walks With A Swagger

API Swagger documentation now displays entity column lists as sample responses, making it easier for developers and integrators to understand available data fields at a glance.


​How To View?

Open up the API Swagger documentation. Find a 'List' endpoint for the entity of interest. Look at example responses to see a list of the column names available.
​


You can then use this to populate your 'selectColumn' entry.


​


Spatial Thinking

Users can now manually export IWP bounding boxes from the model, enabling offline use and integration with external systems that require spatial data.


​How To Do:
From the Model actions menu button (3 vertical dots), click on the 'Download IWP Bounding Boxes.'


And There Is More - Lots More

​In Scope:

  • We Added Scope Start Date and Scope Finish Date fields to CWPs.

  • We added a read-only Scope Start Date field to CWPs, calculated as the earliest planned start date among all direct IWP children

  • We added a read-only Scope Finish Date field to CWPs, calculated as the latest planned finish date among all direct IWP children.

  • Visible to grids and Gantt chart.

  • Both fields recalculate automatically when any direct IWP child's start or finish date changes.

  • Fields will be blank if no direct scope children or dates cannot be obtained (such as blank on the IWPs).

Straight To the Point:
Click on a data diagram mode to navigate to the linked data deliverable.

We Got You Systems:
We added the following additional Dashboard Widgets for Systems Entity:

  • Average Time In Status Widget

  • Bar Chart

  • Data Completeness Widget

  • Distribution Chart

  • Gauge Widget

  • Pie Chart

  • Progress Bar Widget

  • Query Tile Widget

  • Status History Widget

  • Constraints Comparison Widget

Lets Be Direct:
Manpower resources on work packages can now be classified as direct or indirect, enabling more accurate resource planning and cost reporting for project teams.

Optimized:
Optimized the SyncAttributes process for models with thousands of attributes, significantly reducing sync times and improving performance for large-scale projects.
​
​It's A Date!
Date fields for Baseline, Forecast, Early and Late, added for Construction Work Areas, enabling more precise scheduling and tracking of CWA timelines.

​

Doesn't Time Fly?
A 'Next 6 Weeks' time filter option has been added to all Gantt views, making it easier to focus on near-term work and upcoming project activities.


​Moving On!
A right-click context menu option is now available to move tasks between sections on the Task Board, streamlining task management and improving workflow organization.
​
​Lets Make A Group:
Users can now group the Project Gantt view by Construction Work Package, making it easier to visualize and manage work organized by package.

I Need My Space:

Users can now collapse the left-side navigation menu on both the Project Gantt and Gantt views, providing more screen space for reviewing and managing project schedules.
​

​
​You're Special:
Schedule imports now correctly handle date fields containing special characters, preventing import failures and ensuring all schedule data is captured accurately.


​Things Are Looking Up:
Scaffolding can now be created directly from a scaffold request, with the association automatically reflected through a status update, streamlining the scaffold lifecycle process.


​Going Automatic:
The PWP number is now automatically populated on the Construction Components table after a graphical PWP assignment is made, reducing manual data entry and keeping records consistent.​


​I Need More Power - You Got It:
Project Admins can now edit dates, dependencies, and shift successors directly within the scheduling tool, giving them greater control over project timelines without needing elevated system access.

If This 4D Gets Any Better It will be 5D:

The 4D simulation player now supports Baseline, Early Start, and Late Start date options, giving users greater flexibility in visualizing project sequencing scenarios.
​
​Tell Me Later:
Rather than waiting on multiple / large exports to take place, you now have the option to be notified by email or via an in-app popup message when the export is completed.
​


​
​You've Got Mail!
We expanded the User Account Email History - to show not only the last event for that email, but all events (including when the initial email was sent - event!)
​
One for the System Admins!
​
​How to Do:
To check O3 email delivery, open the System Admin context menu in bottom left corner. Go to menu option 'User Admin', Users, open user account from grid (double click on record or select and click on the pencil icon).
With the User Details form open (as below), locate the 'Email History' tab.
Wait for the list to be retrieved.
Note the 'Date' column is now renamed as 'Last Activity Date'. to expand to showing all events for an email - simply double left click on the row / entry.
This will open 'Email Detail' form layout as below example.
​


​
​If you require more information on the above features, please reach out, to your O3 admin or via in-app messaging.