Content
Example Associations - Visualize how your package / entity links to others:
Explanation
What are Associations in O3?
Associations is a term used to describe how the O3 platform manages links between entities (such as Work Packages, Documents, RFIs, User Defined Entity Types, etc).
Note:
Associations can accommodate one to one, one to many, many to many relationships.
Association can link non hierarchal based entities together.
Associations can be setup between entities of the same type
(such as IWP to IWP).Associations can be based on dependency (Predecessor/Successor) and can and supports relationship logic (FS, SS, FF, SF).
What Are Scope Packages?
Scope Packages are, to extent, also like Associations. They typically represent strong, direct entity (parent/child) relationships, such as where there is a hierarchical coding structure.
Examples:
Main Entity | Scope Child/Children | Notes |
CWA | CWP | CWPs are a subset of CWAs |
CWP | IWP | IWPs are a subset of CWPs |
IWP | No | IWPs are not broken down further. |
EWP | Drawings, Documents, Design Work Packages, Vendor Data, |
|
Note for Non AWP: Scope Children are not used in O3 'Work Management' (non AWP approach) projects, which is based on a WBS (Work Breakdown Structure) and Work Orders associated to that structure.
Relationships - Dependency and Relationship Logic
Dependency:
As noted, associations are links between entities. Some relationships may have a dependency, such as entity A has to finish before (Predecessor) entity B can start. Entity C (successor) may have to wait until entity B has started before it can start.
Both Predecessor and Successor relationships can be established in O3.
Relationship Logic:
Relationship logic defines how the predecessor/successor dependency is applied.
Taking the example above, we have described a dependency logic based on a typical Finish To Start (FS), i.e. entity B can only start once its predecessor, entity A has finished. However, entity C can start once entity B has started, which is a Start To Start (SS) relationship logic type.
Relationship Logic Types:
Relationship | Description |
FS | Finish To Start |
FF | Finish to Finish |
SS | Start To Start |
SF | Start To Finish |
Lag:
Lag is the intentional delay between two entities. Such as the Test Package can only start 7 days after the IWP has finished. Lags can be also be applied within O3.
Setup
To use associations we need to state on the project which entity is linked to another (or itself).
To Do:
First, you will need to have role permissions for project settings, or be a Project or System Admin.
Go to Project Setup, Project Settings, Associations and select the entity you want to associate (link) to another.
Then, navigate to the other entity to associate to and click on the 'Enabled' box.
See below for other settings - Association Settings
When done, remember to click on 'Save Changes' button.
Important Note: If you want to see the Association on both entities, you will need to repeat the selection for both of those entities (via 'Choose an Entity Type to manage' selection drop-down)!
Why?: There are scenarios where you may only want to apply / view the association to one entity only.
Lets say the testing team want to link Test Work Packages (TWP) to Installation Work Packages (IWPs). The testing team needs to have the IWPs completed before they can start testing so they will want to select IWPs as Predecessors to their TWPs. However, the construction team may not need to see the testing packages. In this case, we can setup the association on the TWP only. However in other cases you may want to see the association from both entities, so has to be enabled on both entities!
In this example, we have associated Contracts, CWAs, CWPs, Documents, Drawings and EWPs.
Association Settings:
Setting | Description |
Enabled | Turn on/off the entity association. |
Non-Blocking Predecessors | Predecessor entities generate a constraint on the successor entity by default. You can turn this off. |
Allow General Associations | If you only want to have Predecessor / Successor (dependent) associations you can turn this off. |
Allow Predecessors | Allows Predecessor associations to be made. |
Allow Successors | Allows Successor associations to be made. |
Implementation
Lets say we have associated IWPs to itself. When we open an IWP in form view layout we then select the 'Associations' tab (if not shown, speak to your Project Admin to add it to the form layout). Now locate the entity we want to create an association with - in this example IWPs. On the top right of that box will be a '+' button. Click on this and you can:
Add Association(s) to create a general association (see settings) or a dependent association such as 'Add Predecessor(s)' or 'Add Successor(s)'. If you click on one of these, they will be shown in both the Entity association box as well as the Predecessors/Successors box.
In this example, we have added a Predecessor IWP. The entity reference (e.g. IWP number) can be clicked on to jump to the form layout of that entity.
Dependency Adjustments:
Having created a Predecessor, you can double left click on the row to change the Relationship Logic (defaults to Finish to Start/FS).
You can also apply a Lag. For example, it can start 2 days after the the finish
Blocking Constraint:
If enabled in settings, a constraint will also be generated on the successor entity when a Predecessor has been created.
Associations Across All Entities
From the Association menu (under Auditing) you can manage all your associations in one place.
One side of the relationship is shown as Entity Name and the other side is represented by the Associated Entity Name.