Early Planning Content
Early Planning Explained
What do we mean my Early Planning?
In Engineering, Procurement, and Construction (EPC) projects, early planning is critical to ensure project success, minimize cost overruns, and reduce risks. This planning is structured under Front-End Loading (FEL), which encompasses FEED and culminates in the Final Investment Decision (FID). Here’s a detailed explanation:
1. Front-End Loading (FEL)
FEL, also called Front-End Planning (FEP), pre-project planning (PPP), or simply early project planning, is the structured approach used to define a project’s scope, objectives, feasibility, and risks before significant capital is committed. It's fundamental principle is:
Highest influence, lowest cost: Early stages of a project offer the greatest ability to make design and scope changes at minimal cost.
Risk mitigation: Identifies technical, financial, and regulatory risks upfront.
Stakeholder alignment: Ensures all participants (owners, engineers, contractors) share understanding of goals and requirements.
FEL is typically divided into three main stages:
FEL 1 – Feasibility Study
Goal: Assess the viability of a project at a high level.
Activities: Market analysis, technology options, preliminary risk assessment, conceptual designs (“napkin sketches”).
Deliverables: Project charter, high-level scope, preliminary cost estimate (accuracy ±30–50%), initial schedule, risk register.
Outcome: Decide whether to proceed with more detailed planning.
FEL 2 – Conceptual Design / Pre-FEED
Goal: Refine the chosen project option, define scope, and assess feasibility in more detail.
Activities: Process Flow Diagrams (PFDs), preliminary equipment sizing, site selection studies, regulatory assessment, updated cost and schedule estimates (accuracy ±20–30%).
Deliverables: Preliminary design documents, refined cost estimate, updated schedule, risk assessment, preliminary plot plans.
Outcome: Stakeholders make informed decisions about moving to full FEED.
FEL 3 – FEED (Front-End Engineering Design)
Goal: Fully define technical requirements, project scope, and cost to enable final investment approval (see FID).
Activities: Detailed PFDs and P&IDs, equipment specifications, 3D modeling (~30% design maturity), hazard analysis (HAZOP), procurement planning, and schedule freeze.
Deliverables: Comprehensive engineering design documents, detailed cost estimate (±10–15%), project execution strategy, risk mitigation plans, Basis of Design (BoD).
Outcome: Provides a robust, frozen project definition, ready for FID.
2. FEED – Front-End Engineering Design
FEED is a subset of FEL, often referred to as FEL Stage 3, focused specifically on engineering precision and scope definition necessary for construction. Key aspects:
Scope Definition: Freeze configuration and specifications to prevent costly changes later.
Cost Estimation: Achieve a high-accuracy Total Installed Cost (TIC) estimate, typically within ±10–15%.
Risk Management: Identify technical and constructability risks, safety, and compliance issues before procurement and construction.
Procurement Planning: Identify long-lead items and plan vendor selection. See Logistics Strategy.
FEED results in a package that allows contractors to submit bids with confidence in scope and quantity, reducing errors, change orders, and schedule slippage during execution.
3. FID – Final Investment Decision
FID is the formal authorization by the project owners to commit capital for the execution of the project. The decision is based on comprehensive FEL/FEED outputs:
Assurance of design maturity and cost accuracy
Clear identification of risks and mitigation plans
Alignment of stakeholders on objectives, scope, and schedule
Market, regulatory, and financing considerations
At FID, the project transitions from planning and definition to detail design/engineering, procurement, construction, and commissioning and startup/handover, typically under an EPC framework.
4. Benefits of Early Planning (FEL + FEED)
Reduced Costs: Early identification and resolution of design and scope issues.
Risk Reduction: Technical, financial, and regulatory risks addressed before execution.
Improved Schedule Predictability: Fewer changes during construction.
Stakeholder Alignment and Decision Support: Clear decision gates at FEL1, FEL2, and FEL3 reduce conflict.
Agreed Path of Construction: So the project team know in which order the project will be executed, ensuring safe access for equipment installation and workers and assisting alignment of site expectations with procurement schedules.
Optimal Resource Deployment: Ensures long-lead items, labor, services (etc. cranage/lifting, shipping and fabrication), and materials are correctly identified and provided on time (aligned to path of construction).
5. Summary
Early planning in EPC projects through FEL, FEED, and FID ensures that:
Concepts are viable and feasible (FEL1/FEL2)
Engineering requirements are clearly defined (FEED/FEL3)
Financial and technical commitment is justified (FID)
Investing effort in these early stages reduces uncertainties, improves cost control, and enhances project outcomes during the highly capital-intensive construction and operational phases.
Analogy:
Think of FEL as mapping the entire route of a long journey before buying the car. FEED is detailing the car, fuel, and itinerary. FID is the point where you decide, “Yes, now we start the journey,” having minimized detours, risks, and unexpected expenses.
By following this structured and phased approach, projects are better positioned for timely and successful completion.
Other Considerations - Logistics Strategy:
Early planning on projects should consider the process of integrating logistics to identify, for example, transport requirements, permitting, weather/environmental/event windows, shipping routes, aggregate supplies, and lifting strategies, alongside the early engineering phase.
For example, what shipping routes may be viable to enable pre-fabricated modules to be delivered from the fabrication yards to site (shipping routes, border crossings, conflict zones, permits, available ships, weight, width, height and depth, canals - bridge and lock clearance, receiving port facilitates and transfer areas, cranage (specialist heavy lift availability), rail access (aggregate supplies) and road access (reinforcement, new road routes to site, site traffic/congestion, laydown areas, parking and temporary facilities and airport access). Also, consideration for staff transport and on-site accommodation and specialist contractor temporary works and storage areas.
By planning logistics early, projects can eliminate rework, reduce costs, and get the project to market faster. This proactive approach ensures that the infrastructure is delivered on time, on budget, and without surprises, contributing to the overall success and reputation of the project.
The logistics will also factor in the Path of Construction. For example, if the main site access is on the East side, you may want to construct from the West side working back towards the East side, so that access is not blocked during execution!
How O3 Supports Early Planning?
O3 Early Planning Toolset Overview
O3 recognizes the significance of early planning and how it is critical for future project success. The insightful decisions and preparedness for executing the project made early on helps with streamlined project execution, with reduced delays and keeping within budgets.
O3 has a dedicated set of tools accessed from the 'Early Planning' menu on the project navigation menu to assist. These include, but not limited to:
O3 Tool | Description |
AWP Matrix | This is a list of CWAs set-up from which you can generate packages. |
AWP Matrix Index | This shows what has been set up on the project so far, such as CWAs, Disciplines, CWP, EWPs, VWPs, PWPs... |
Construction Work Areas | These are the first packages established and generally quite broad in scope and geographic accountability, and are then broken out into CWPs, EWPs, IWPs, etc. |
Path of Construction (POC) | This guides you through the process of Early Planning, including Plot Plan uploading, creating CWA Boundaries, Linking the boundaries to CWAs, Sequence CWAs and Review Initial POC. |
Plots Plans | Load your project plot plan or download a map of where the site is to be situated in lieu for now. |
CWP Matrix | When ready, you can break down the CWAs to CWPs using this tool. You can decide if you need certain Disciplines or Purposes to be represented on the CWA. Tick the ones you need, and generate the packages. You can also see what you already have setup. |
CWPs | If you want to just add CWPs without a guide or edit or review existing ones, you can use this option. |
Team Boards | This allows for the grouping of related tasks in one place where they can be progressed, monitored and shared, supporting a collaborative approach. |
Other considerations include the integrated Risk Log, Team Goals, and you can also create your own, custom O3 package types with User Defined Entity Types, as they may support your organization's Early Planning and beyond requirements. This might include support for Logistics or temporary facilities. You can also add Dashboards to report out the status of your Early Planning activities, including custom packages.
O3 Early Planning Toolset - How To Use Guide
The following section goes into more detail on how to use these Early Planning Tools:
AWP Matrix
If you are new to AWP, try the AWP Getting Started Guide for more information.
AWP Discipline Set-up
First of all, you will need to configure which disciplines are applicable to the AWP Matrix.
How To Do: With the appropriate project access permissions (such as being a Project Admin), go to Project Setup, Project Settings, Disciplines and then go to the AWP Master Index tab.
Click on the '+ Add Rule' button. Give the Rule a name and description. Then click on Add Package.
For say CWA, you will typically want to generate CWPs. But it is possible to extend this to other package types. CWPs can be broken down into packages such as IWPs. See CWP Matrix.
You can auto set a Purpose on the package.
When you generate packages, O3 will need to know what type of mask to use for your package number format. Example: {{CWA}}-{{Discipline}}-01 - which would take the CWA parent number, hyphen, the Discipline, hyphen and then typically a number. An incremental counter (to ensure each package is unique) is ignored ( {{CTR}} ) because the AWP Matric will only create one package for that CWA - Discipline combination!
This should generally align with the e.g. CWP Mask setting as applicable.
Lastly we can provide a default description, such as if this is a Piping discipline package, we could say e.g. 'CWP - Piping'. In this case, we have a discipline code AA and called the description 'CWP - AA -'.
After the rule is created:
To Generate The Packages:
Now that the Disciplines are set-up, they will be shown as available on the AWP Matrix. If you do not see Disciplines shown at the top, none have been setup per the above instructions!
How To Do: On the Early Planning menu, select AWP Matrix. If you want, you can filter the horizontal list to specific Disciplines across the top, or all will be shown. Now to create packages, select either the CWA on left to select all disciplines (shown), or work vertically down a discipline and select for specific CWAs that will include that discipline.
Note: where a package already exists for that discipline, a tick will already be shown!
When the selection is made, click on the Generate Packages button on top right to create the packages.
AWP Matrix Index
The AWP Matrix Index is your guide to what packages have been created in O3, as it supports the pre-construction execution and support Early Planning stage.
This includes CWA and Discipline combinations and then the packages within that criteria: CWPs, EWPs, VWPs, PWPs. Each of these packages can be individually selected (clicked on) to open.
How To Do: From the Early Planning menu, click on the AWP Master Index. There is a refresh icon in the top right to show the latest updates.
Construction Work Areas
CWAs are typically the top level of the AWP package hierarchy, and are used for Path of Construction (POC) approach. They provide a broad overview of execution strategy intent and scope allocation. This could be a Tank Farm area or the power backup facility provision of a Data Center.
CWA Setup:
Before you start creating CWAs, you should configure these from the Project Setup section. The CWA setup can be configured by Project Admins / System Admins or those with access permissions to Project Setup.
Click on Project Setup - Project Settings - Entity Settings and then CWAs. From this screen you can configure the number mask, Data Requirements, Statues, Approval Types, Stages and Development Step Types for example.
Now that the CWAs are created you can add and edit your CWAs.
How To Do: From the Early Planning menu, click on Construction Work Areas (CWA).
From here you can click on '+' to create new CWAs or edit exiting entries shown in the list.
The grid view selector can be used to see different Grid data, such as by Components.
If you double click a CWA row on the grid, you can open the record in Form Layout view.
Tool Bar: To see other data related data, click on the tabs shown (Associations (links to other data entities), Approvals, Gantt view or see the change history).
Other Tool Bar menus, i.e. Materials, Documents, Deliverables, Scope Packages, Constraints, and Attachments can be added, by request to your Project Admin, who can modify the form layout to suit the project requirements.
Path of Construction (POC)
The Path of Construction option is an Early Planning guided (wizard) approach, to help you get started. You can be guided by adding a plot plan and creating CWA boundaries.
CWA Note: This process will allow you to create new CWAs on the fly, or you can link to existing CWAs created previously. If you are creating new, see Construction Work Areas section regarding configuration, such as numbering masks and Statuses. Units are tied to plants and plants can have one or more projects linked. Speak to your O3 System Administrator to define these settings. To modify the new CWA form layout, contact the system/project administrator to ensure any mandatory required fields are added to the form layout!
Upon clicking this option, you can click on start by adding an image, document or drawing.
Stop - Start Note: You can stop the guided process and resume where you left off at a later time! The POC is an optional guide to assist set-up, however you can, for example, go directly to the CWA grid to define your CWAs and / or Plot Plans to define your CWA boundaries option. For new users, this guided process is recommended.
Select the file that can best describe your project outline (plot plan/map of site, document outlining the scope or a drawing representing the proposed project).
Tip: A top down, flat view of the project site generally works better over an isometric / 3D view. This will aid in drawing CWA boundaries!
Plot Plan Example:
Let's start with a plot plan. We select the file, added a name for the plot plan and a description. We then click on the 'Path of Construction' button.
Page Numbers: If you are importing a PDF file, and that file has 3 pages and the plot plan you are importing is on page 2, you can specify 'Page Number' as 2, for example.
Define the Boundaries: Having loaded the plot plan, the next step is to define the CWA boundaries.
You can use the tool bar across the top to select a shape that best matches the area, be it a circle or rectangle in the example below.
Here, we intend to make a Construction Work Area represent the Area 1: Production Tank Farm on the plot plan. You can use the border nodes to resize the shape to match the underlying plot plan area, as well as the rotate option at the top of the shape.
Now we have created our main CWA boundaries, Areas 1-4 plus the main pipe rack in this case. Note it is also possible on the Object Properties pane on the right side to change colors, border size and opacity.
Now, we can click on the 'Complete Boundaries' button top right.
Now we will be prompted to link the shapes (boundaries) to CWAs.
Linking Boundaries to CWAs:
Click on the shape to link (see object properties on right to confirm selection). Now you can link to an existing CWA, or create new ones via this guided process.
In this case we are creating new CWAs. In this example, we have linked the Area 1: Production Tank Farm to a new CWA-1 entry. Click Save to Continue.
With the new CWA created and linked we can repeat this with the other shapes drawn. You will also note an option to Unlink existing CWAs, such as if linked to an incorrect CWA.
Also note that linked shapes will show a label indicating what it is linked to!
If linking to existing CWAs, you will be presented with a list (if any exist at this time). Let's say we have already created CWA-2 previously. Click on the row and then click on Choose Items button at bottom.
You can save (Save Changes) your current changes at any time and come back later or click on the 'Complete Linking' button to proceed to the next step.
CWA Sequencing: Having completed mapping the plot areas to the CWAs, we can now determine in what order these CWAs will be executed (installed/built etc.). Click on 'Continue To Sequencing'.
As noted, the initial sequence will be proposed to be the same order the boundaries were linked. However, let's say site access is to the Northeast (top right) and we want to work from the Southern end back to the access road. Click on the 3x3 dot button, and drag the CWAs to the order they will be constructed. In this case, we will start with Area 4 (CWA-4), then the Pipe rack (CWA-99), then Area 1 (CWA-1), Area 2 (CWA-2) and finally Area 3 (CWA-3).
Sequence adjusted to reflect desired path of construction based on access during build.
When done, click on the Save Sequencing button.
Confirming the Sequence can be saved. If OK, click 'Save and Continue'.
Finally Review your Path of Construction.
When happy, click on the 'Complete Review' button.
Complete Review: One final confirmation check. If all good, click on 'Save and Continue'.
The guide is now complete.
If you select the 'Path of Construction' option again you can repeat from the start, perhaps with a new plot plan / different scope, etc. If you were part through the guide, then you have the option to resume where you left of from. If you want to edit the Plot Plan just created, go to the Plot Plan menu option (see next section).
Plots Plans
How to Access: From the Early Planning menu option, select Plot Plans. If you are new to the process, we would encourage using the 'Path of Construction' guided instruction (see previous section).
If you have already created a plot plan/s you can see them listed on the grid, and edit them accordingly, or you can create a new plot plan.
Tip: A top down flat view generally works better over an isometric (3D view), as better supports setting boundaries for entities (like CWAs).
Note that plot plans can also be created to reflect more detailed Construction Work Packages (CWPs) and other entities such as for Testing (TWPs), etc.
Adding a New Plot Plan
Click on the '+' button to create a new one from the top right. Then provide a name and description for the plot plan.
Choose the background. This could be a plot plan static image (such as a plot plan or map of the project site), a plot plan drawing or a document.
Page Number
If you are importing a PDF file and that file has 3 pages and the plot plan you are importing is on page 2, you can specify page number 2. When ready click on 'Create.'
Editing Existing Plot Plans
Having opened an existing plot plan we have some options at the top.
Display Mode (*Plan View): Default, Work Package Status or Constraint Status.
Association Type: You can focus to show just certain entity types (for example, may only want to see CWPs or Systems).
View Mode: *Plan View (for reviewing), Configuration View (to Edit), Timeline View (to see entity sequencing over time), Path of Construction View (Sequencing).
Configuration View - Toolbar:
To set boundaries in 'Configuration View,' you can use the toolbar at the top to create shapes to represent the entity scope. This could be rectangle, circle, triangle or polygon (useful for custom shapes, such as L shapes. return to starting node to complete the shape). You can also add images and text to the plot plan.
Other Toolbar Options are available after selecting a shape -
Link: Select an entity type and then specific entry to link the shape to (package, system).
Lock: You can Lock the shapes to accidentally avoid selecting / moving shapes.
Deselect: Deselect current shape.
Center: Will move the shape to the center point, horizontal or vertical center of the Plot Plan.
Z-Index: Provide options where you have overlaying shaped such as to bring one to the top, bottom or up or down a layer position.
Delete: Remove the shape from the plot plan.
Properties Buttons: In top right for Diagram, Object (shape) Properties and Layers.
Object Properties pane on right side, such as colors, borders, opacity.
You can click on the Diagram button to see the overall Diagram properties.
Layers: Can be useful for collecting shapes at different levels. For example, CWAs might be on Layer 1 and CWPs on Layer 2.
Example: In this case we will expand upon the Path of Construction example and breakdown the plot plan further to CWPs...
Existing Plot Plan/s Listed:
Let's Open Site Overview 1.
We can change the Association View to CWPs first. The shape (Boundaries) linking to Packages is independent, but focusing on a single package type can make the working area tidier by hiding the CWAs/other package types for example.
With All/CWA Associated View entities:
Switching view to CWPs: Now at this point, no CWPs have been defined so the plot plan shows no annotation. The CWA boundaries are now no longer visible.
Editing: As we are editing the plot plan, we need to switch the view to 'Configuration View.'
Using the Toolbar - Shapes: in this case we are using the circle shape as best matches the product tank / vessel. We can use the border nodes to resize to match and if needed, we can rotate the shape with the top node.
Linking Shapes/Boundaries To Packages: We can now select a shape and use the Tool Bar to select 'Link.'
In this case, we will select CWP (as noted, the 'Association Type' in top right does not inhibit linking to other entity types, but if different, will not show!).
You are prompted to select an existing CWP or create a new one on the fly. Here we have added a new CWP.
Remember to Save Changes.
CWP Matrix
The CWP Matrix offers different views. First, the matrix is shown by CWA. You can then select Discipline or Purpose.
Discipline or Purpose option.
Want to create packages? You can switch to Plan View and enter the number package.
Let's say we want two CWPs created for a particular CWA and a Discipline. At the intersection, put in the number of packages (example 2) to create.
When ready, click on the 'Generate Packages' in the top right.
After you click 'Generate Packages,' you can also generate equivalent EWPs and PWPs at the same time. If you just want to generate CWPs at this time, simply click on 'OK, continue' button.
This will create an import file and process it. Once complete the packages are generated.
Want to create a discipline or purpose on the fly? Click on the '+' button.
CWPs
A Construction Work Package (CWP) is a manageable segment of work that is clearly defined and assigned within a Construction Work Area (which is a larger segment of the construction project).
It serves as a fundamental building block in project management, allowing teams to break down larger projects into smaller, more manageable units. Each work package typically includes a defined scope, budget, schedule, and deliverables, making it easier to track progress and accountability.
The CWPs can be entered manually, imported or generated as part of the AWP Matrix, which can generate CWPs per discipline requirements for selected (or all) CWAs. You can also use the CWP Matrix to generate CWP Packages based on discipline or purposes.
CWPs can be reviewed and edited via the CWP grid.
Having opened the CWP Grid, you can filter, sort and group. Export the list or open a particular CWP for the form view layout.
CWPs can be accessed via the Early Planning and Work Packaging menus (as selected within the project settings).
You can also switch the grid view, such as to see CWP components or materials.
Having opened a CWP in form view, you can review and update the CWP attributes. Use the tab bar for additional views and access data such as Status History, Constraints, Approvals and Documents.
The actions button (3 vertical dots) offers a menu of additional functionality, including Cloning, creating EWP and IWPs, Generate a Detail Report (CWP based).
Team Boards
Team Boards can be used to manage Early Planning Related Tasks, which in turn can be used to achieve stage gates, such as FEL, FEED and FID, as well as can be used for Early Procurement and Logistics planning and temporary facility planning.
Team Boards can represent your tasks in different formats, such as card view (Kanban), section lists, grid, calendar and Gantt formats. You can interchange between these formats at any time based on what works best for your organization or approach.
See Here for more information on Team Boards.
I'm not using AWP... How is Early Planning Supported?
O3 Solutions recognizes that not all projects will want to run using the Advanced Work Packaging (AWP) approach.
As an option, O3 projects can be setup for Work Management, which is based on a WBS (Work Breakdown Structure) and Work Orders (which can be treated as work packages) approach.
In this case, the AWP and CWP Matrix and guided Path of Construction options are not applicable, but you can still use other O3 tools, such as Plot Plans, custom packages (User Defined Entities), Team Boards, Risk Log, and report out with Dashboards, etc.