Skip to main content

Release Notes 26.1

Released 7th January 2026

Written by Roy Abery

Welcome to the first release update of 2026 - 26.1.


Ensuring you have the correct version running!
If you don't see 26.1 in the bottom left corner - please clear your browser cache.
​


What's New - Table Of Contents


Connected by Design

You now have the ability to constrain a package like a CWP or IWP with an Interface.
​
​First, you can now setup interface associations:
You will need to be an administrator or provided the permissions.
​
​Where to Set-up:
Project Setup, Project Settings, Association Settings.
​
The association set-up is one way. So for example, a CWP to Interface Point association, you should add the Interface Point association to the CWP and then add the CWP to the Interface Point (unless you only want to see the associations from the CWP or Interface Point).
​


To set up a constraint, also ensure your association allows for predecessor/successor relationships.
​


​​Secondly, we can now constrain the package to the Interface Point.
​
​How to Do:
Open your package that is tied to the Interface, go to the Associations tab. Select the Interface box and click on '+' button. Then select, for example, 'Add Predecessor'.
​


In this example we have set up a Predecessor Interface Point to an IWP. This automatically creates a Predecessor constraint. This can be auto completed when the Predecessor (such as the Interface Point) is completed.

​


Find What Matters, Faster

You can now add filters to the Schedule - Schedule Activities - Outline View.


Jump To It

You can quickly jump to external websites on RFIs. For example, you may have an external system managing Non Conformance Reports (NCR) and want to jump to that website and depending on the address, perhaps to a specific NCR record.
​

You can add the 'External Link' to both your form and grid layouts. The hyperlink supplied shows in a different font color.
​
​External Link on Form Layout (if not shown then the form layout will need to be updated by an admin):

External Link on Grid Layout:


It's Urgent

We have added the Urgency field to RFIs for reporting.


The configuration for the Urgency can be edited in Project Setup, Project Settings, Entity Settings, RFIs.
​
To make the granularity more suitable for RFIs, Urgency is set-up based on days.
​


Task ID Visibility, Defined by You

You can now switch on / off the the 'Task ID from 'List View' and 'Card View' team board layouts.
​
​How To Do: On the Team Boards, click the action button (vertical ellipses button in top right) and if in List View or Card View you have the option to 'Hide Task ID' or 'Unhide Task ID'.
​

List View with Task ID hidden:


Real Dates. Real Progress. Real Insight

You can now report progress charts by the progress (step) claimed date or when the progress was entered date.
​
​Why is this useful? Perhaps the execution step was completed last week (which maybe is in last month's reporting period), but the person entering progress data, is entering the information in the following week when its been collated or advised.
​
By reporting the claimed date, more accurate reporting can be obtained.
​
​How To Set-up: open a dashboard progress curve widget. These are available for most entities (see example below).
​

When the widget is added to the board (or already exists), click on the

action button (ellipses) and then Settings option.
​

Locate and click on the 'Earned Hours Basis' for the drop down selection.
​

You can now switch this to 'Step Completion Date' or 'Progress Entered Date'.


Comparison Example:
​


​


Set It and Forget It

Your ideal 3D Model 'Selection Resolution' can now be saved with your layout.
​
​How To Do:
Open a model. Click on the Filter button above the model tree on the left side of the screen. From the filter menu select 'Selection Resolution'.
​

Then make your selection/s.

After you apply you will be prompted to save the layout or click on the Layout button and save from that menu.
​


Gantt Hide and Seek

You can now turn on/off the bar labels in Gantt Chart View.
​


​

How To Do:
When you have a Gantt Chart view, locate the layout button (normally in top right of chart) and there should be a Hide / Unhide Labels option shown. Click on this to toggle on or off.
​

Example of Label toggle from the Team Board Gantt View:

Example of Label toggle from the Schedule Activities Gantt View:


Let's See The View First

The Viewer Tab is now shown as default when opening a drawing in the form layout

Drawing Viewer Tab is now shown first by default.


Respect The Hierarchy

During the creation of an IWP/EWP, the user will only see and select those CWPs applicable to the CWA selected for said IWP/EWP.


​Example: Create an EWP. Select the Construction Work Area (CWA).


Then select the CWP.
The chooser grid is then showing only those CWPs that match the same CWA selected. This helps to make the list to choose from shorter and more manageable.
​


It Started With?

The Model Parser Object Filter now has options for 'Starts With' and 'Ends With'.


I'm On Board With This One

You can now view your IWPs in a Kanban style Card View, by Status.


You can use the quick filters in the top right for e.g. CWA, Discipline and Purpose, etc.
​


​Note: The card, board view is restricted to first 200 entries to make the board more manageable.
​


We Speak Your Language (我们说您的语言)

The O3 interface now supports Mandarin language support.
​O3界面现在支持普通话语言。


​How to Do: Click on the Language button (globe) at top- right and then select the language you want.
​操作方法:点击右上角的语言按钮(地球仪),然后选择你想要的语言。


We Got New Rules

We have added new value builder rules 'Save Named Value'. You now have the ability to e.g. multiply one saved name value to another.
​
​Example Schedule Activity Import File (see Parse Test column):


​Field Mappings Example:
Here we have set-up a configuration for 'Outline Number'.
We have saved the Width and Length values ('Save Named Value') and then determined (evaluated) the Width x Length value and made this the outcome to be stored in 'Outline Number'.


​Test the Configuration.
'Outline Number' is shown as the value of Width x Length.


You Have a New Package - Setting

You can now establish in settings which entities the package requires when being created using the 'WFP Guide', such as Approvals, Constraints, Documents, Resources, etc.
​


​​How To Do: As an Admin or someone with project setting permissions, under Project Setup - Project Settings - Package Builder.
​
Click on which entities the package should prompt to add.
​

Example: Being prompted to add Construction Equipment while creating a package.


Accountability By Design

DWP (Design Work Packages) now have Execution Tasks and these can be assigned to specific users.
​


The Execution Task Types are defined by admins or those permitted permissions to edit Project Settings.
​

Go to the Project Setup, Project Settings, Entity Settings, DWPs (Design Work Packages). Then go to the 'Execution Task Type' tab. To add - click on '+'.
​


When creating the task on the package, you can now assign the task to a user.
​
​Note: If not shown, the form layout may need to be edited to add the assignments in!
​


Expand, Contract, Expand, Contract...

You can now quickly and easily expand and contract the Schedule Activities outline view groupings.
​
​Outline View expanded:


​Collapsed Outline View:


Where is my (AI) Assistant?

For those companies signed up to AI usage, the AI Assistant Tool is now available and access can be further controlled via user permission Roles.
​
​How To Do: System Admins can open the User Admin, Roles, open a role for the form layout. Then scroll down to 'Tools' and then across to the 'O3 Assistant'.


​
​


Everything Else...


That's My Property!

We added in some additional bill of material properties:

  • Commodity Code

  • Commodity Description

  • Specifications

  • Class

  • Material Sub Category

These can be found in the Data Requirements.
​

I've Scheduled That!

We added Schedule Activity ID as a field on PWPS (Procurement Work Packages.

That is Bound To Work

Last, but not least, we added the ability to export bounding boxes for subcomponents. That's one of the precursors to help with object relations.


From the O3 Solutions Team.
​
​Have a Safe and Successful 2026