Skip to main content

Release Notes 25.18

Released 3rd September 2025

Written by Roy Abery

Make sure you're using the correct version of O3! The version number is located in the bottom left corner!
​

If you don't see version number 25.18 in the bottom-left corner, please clear your browser's cache and refresh.
​


​


Table of Contents

  • Going Mobile with ONField
    Our mobile application has been re-released. This new application is available on Apple and Android devices. The first release is focused on IWP progressing and works both online and offline

  • Spoiler Alert!
    Model Grid - Model Preview Pane​ now available.

  • You're Certified
    We have added the ability to tie in test certification documents (such as used with Inspection Test Report Check Sheets) to Execution Task Steps and Work Packages.

  • The Entity ID
    You can now determine the entity ID of an IWP from the IWP Grid.

  • Just What's Mapped
    You now have the option to only consume the fields mapped on a Data Deliverable.

  • Show Me The History
    The Status History can now be added to RFI and User Defined Entity form layouts.

  • By Association
    You can now, on the Documents tab, add an association and define what type of association (e.g. Predecessor) it is from the sub menu.

  • Delivery Service
    View a 4D visualization for material arrival to site.​​

    • Discipline can be used on RFI Masks.

    • On version controlled projects, revision numbers with a leading alphabetical character will now autoincrement.

    • Risk Mitigation Notes on Risk Log - Free text Field (Risk Mitigation Plan is a text loop up).

    • The Graphical Package Builder has been updated to eliminate the need to scroll to see hours and quantity totals when adding components.


​


Going Mobile With ONField


We are pleased to announce we have a new O3 Mobile App, 'ONField'! ONField is available on both the Apple App Store (Apple iPhone / iPad devices) and Google Play (for Android based devices) download sites.
​
​Note: The external links provided below are supplied in good faith, but we are not responsible for their content or availability. If you wish to manually locate these, go to your chosen application store and search for ONField by O3 Solutions.
​
​Apple Store: O3 ONField on the App Store
​Google Play: O3 ONField - Apps on Google Play
​
​About: O3 ONField brings the power of O3’s capital project management platform directly to your mobile device. Built on industry-leading practices like Advanced Work Packaging (AWP), Agile, and Lean, O3 empowers teams to drive performance from planning through startup. Designed for the realities of the jobsite, ONField enables key workflows—such as IWP progressing—even when offline, ensuring productivity in low-connectivity environments.
​


​In Summary:
Our mobile application has been re-released. This new application is available on Apple and Android devices. The first release is focused on IWP progressing and works both online and offline.
​
​Want More Functionality?
If you have a requirement for O3 mobile functionality, we can look to address that.
Please contact support@o3.solutions or contact your O3 Project Manager or O3 Solutions client contact if you have questions or would like to learn more!


Spoiler Alert!

The Model Grid now has the ability to show a model preview pane.
​
​How to Do: On the Models grid, click on the Actions menu button (3 x vertical dots/ ellipses), and click on 'Show Preview' from the menu.


​


​

The preview pane is shown on the right side of the screen. Click on a model to see a preview.


​


​

​Note: The preview will be centered around the Autodesk set Home position, so for example, if that were to be a significant distance underground then it will show the above ground part of the model accordingly at the top, like the example below.
​


​


You're Certified

We have added the ability to tie in test certification documents (such as used with Inspection Test Report Check Sheets) to Execution Task Steps and Work Packages.
​
​Implementation Basis:
​

  1. Templates: You define the test certificate check list template documents and load them into the O3 Documents grid (these will be blank / to be filled in). These templates can be loaded from a Document Management System into O3.

    1. Example: lets create 3 template documents called A01, A02, A03 (this would be the Document ID).

  2. Configure Execution Task Steps: In O3, you define which execution task steps are tied to one or more certificate template documents. We set up a mask for future document name matching.

    1. Example: Lets say we have an execution task type called 'A-Inspections' and has Step 1 being tied to certificate template A01 and Step 2 is tied to certificate templates A02 and A03.

    2. We create a mask for future document matching using our organizations naming convention e.g. Certificate-##{{TemplateDocumentID}}-##{{IWP}}. We can use this same mask basis or all 3 templates in this case.

  3. Assign Templates To Work Packages: You can (optionally) assign the certificate template document/s to a work package for printing off later. Note: Omitting this assignment does not impede late step to certificate matching, but otherwise assists the team working on the work package!

    1. Example: For e.g. IWP-01 we assign test certificate templates A01, A02 and A03 from the Documents grid. The field team later print these off and take them into the field.

  4. Perform Tests and Return Results: The Inspection Team print off the certification templates and update them in the field/location where test to be made. They are returned and scanned into the Document Management System and given a document name that identifies the certificate template and the package the test / inspection was carried out on.

    1. Example: A01 check was postponed, but A02 and A03 checks were performed on work package IWP-01 and returned for scanning and loaded into the Document Management System. They are named 'Certificate-A02-IWP-01' and 'Certificate-A03-IWP-01'.

  5. Upload Test Certificate Documents and Link to Execution Task Steps: The Document Management System documents are loaded to O3 (or can be manually created in O3). O3 uses the Execution Task Step template 'Mask' as a means to identify the package and execution task step that ties to that updated test certificate document number.

    1. Example: We upload document 'Certificate-A02-IWP-01' and 'Certificate-A03-IWP-01' to O3. We go into the work package IWP-01 and against Execution Task 'A-Inspections' we see that Step 1 is still pending 'Certificate-A01-IWP-01', but for Step 2, both A02 and A03 certificates have been added to the O3 Documents grid.

Note: The updated certificate document uploaded to O3 would be considered completed. O3 will only look for a document name match to the task step mask entry and not consider the document's status. The certification steps can still be progressed but the package can not be moved to a complete status if it has outstanding test certificate documents.
​

Getting Started...

Prerequisites: You will need certificate document template/s uploaded to the Documents grid.

  • This should be e.g. a blank check list template.

  • Consider a Document Type to better filter the empty templates vs the filled in templates / certificates for selection later on.

Mask: The template Mask* setting (*described later) will be used as a means to tie a filled in test certificate document to a work package and execution step, so please review and align with your organization's document naming convention (the Documents grid will end up containing both blank and filled in test certificate templates).
​
​Configure Execution Task Steps:

  • Configure the Execution Task (will need to be Step based).

  • Navigate to Project Setup - Project Settings - Entity Settings - Work Package (e.g. IWP) - Execution Task Type.

  • Then either create a new entry or edit an existing entry that will be based on Step progress!


​


​

Now navigate to the Execution Task Steps. Against a step (or add one), there is a new 'Add Certification Document' button.


​Template File: Now select the Template Document with the '...' button from the Documents grid.
​
​*Mask: Then set up a mask for the completed test certificate document naming being generated. It is good practice to use ##{{TemplateDocumentID}} for the template document id and the Work Package reference e.g. ##{{IWP}} or ##{{TWP}}. You can place this in reverse order and you can add static text.

  • Example: Test_Certificate_##{{TWP}}_##{{TemplateDocumentID}}

  • However you define it, it needs to match your document naming convention for the process to work!
    ​

​
Here we have added two certificate documents to the step we launched this from.


​Important Note: Click on Apply. At this point, the configuration is not saved yet so when you return to the Execution Task Type Details form, click on the 'Save' button at the bottom!


​

Reflecting Test Certificate Document Updates

Assuming we have recently added Test Certificate Documents to O3 Documents Grid...

  • Open the work package in form layout view. Go to the 'Execution' tab.

  • Open an Execution Type with steps tied to a Test Certificate Document/s.


​

You will now see a column called 'Certification Documents'. If the expected document is uploaded to the Documents grid, it is shown as a green circle and tick mark, otherwise it shows an orange circle with an explanation mark.


​

If we try to change the status of the main Task where the steps belong to 'Complete', and there are outstanding certificates, you will not be able to save the task. You will get a message like below. However if the task is still open (status), you can still claim step progress and Save.


​


The Entity ID

When you open an individual IWP in form layout view, you will see an id reference in the URL.
​
​Example URL (IWP ID in bold):
'https://test.o3solution.com/#/projects/28/work-packaging/iwps/34634/summary'
​
You can now determine this entity ID from the IWP Grid by adding the 'ID' column.
This can be useful for API calls for example where you need to reference the specific IWP ID number. With the ID available to the grid, all IWP IDs can be exported for example at once.
​
​ID is actually now available as a column on most data grids. This will also allow users to update the names of their work packages and other entities!


Just What's Mapped

You now have the option to only consume the fields mapped on a Data Deliverable.
​
​How To: From the Data Deliverables grid, open the Data Deliverable for form view. Click on the Actions menu button (3 x vertical dots / ellipses) and click on 'Configure Field Mapping' from the menu.
​


​

At the bottom of the screen is the 'Only Use Mapped Fields'. Tick this option if you only want the mapped fields to be considered when transferring data.


​


​


Show Me The History

The Status History can now be added to RFI and User Defined Entity form layouts.
​
​How To Do: Open e.g. the RFI / User Defined Entity from the grid layout for the form layout view (it does not matter which record you open.) Now, click on the Form button and the form to be edited.
​


Go to the section you want to add the status history to and search for 'Status History'.


​

You can then move it and resize accordingly.


When complete, click on the form button again and click on the Save or Save As option to save the Form layout.


By Association

You can now, on the Documents tab, add an association and define what type of association (e.g. Predecessor) it is from the sub menu.


​


​


Delivery Service

View a 4D visualization for material arrival to site. This is useful for Long Lead / Major equipment Items.
​
​Basis: Bill of Materials (BOM) - Required At Site Date (RAS Date) as the target vs either the Forecast Arrival To Site Date (if Arrived At Site Date is blank)or the Arrived At Site Date.
​
​To Do: Open a model. Select 4D View, Change Display Mode to 'Component Material Arrival to Site' and then select 'Visualization'.


​


​

Note: this feature is an addition to the 'Component Material Percent Arrived' 4D view provided in the previous 25.17 Release Notes!


There is more...

  • Discipline can be used on RFI Masks (For Project Admins)

  • On version controlled projects, revision numbers with a leading alphabetical character will now autoincrement.

  • Risk Mitigation Notes on Risk Log is a Free Text Field (Risk Mitigation Plan is a text look up).

  • The Graphical Package Builder has been updated to eliminate the need to scroll to see hours and quantity totals when adding components.



​


​

Did this answer your question?