O3 has introduced a new workface planning 'Look Ahead' option for a 30/60/90 view of CWP releases, IWP Development and IWP Releases to support Construction Start.
When entering progress on quantity-driven execution tasks, users can now see the total units for reference.
Users can now set a “Discipline Category” on their disciplines to manage a parent discipline/discipline relationship.
Users can now create Disciplines and CWP Purposes directly from the CWP matrix!
Data Review entries can now be quick filtered by “Added Components”, “Updated Components”, and “Deleted Components” using the 'Change Type' column field.
Users can now configure the IWP Constraints Bar Chart widget to show the number of hours remaining.
There's More...
Summary of other changes incorporated into this release.
Seeing Into The Future
A new Workface Planning 'Look Ahead' option is now available for projects to review CWPs that are pending release (executing in the next 90 days), IWPs that are pending development (executing in the next 60 days), and IWPs that are pending release to the field (30 days or 3 weeks).
How To Access:
From the Projects Navigation menu, select the 'Workface Planning' menu, and then select 'Look Ahead.'
Look Ahead Timeframe: From the above drop down you can select the Look Ahead timeframe.
Data View: Switch between Grid and Gantt view.
Advanced Options:
You can select the dates based on Baseline within timeframe and also include entries that were originally scheduled for the selected timeframe, but no longer included (planned dates changed).
The Advanced Options applicable (as selected from the drop down), will display the matching legend key color, highlighting the row/s that match the criteria.
I'm Driven By Quantity
When entering progress on quantity-driven execution tasks, users can now see the Total Units for reference. You can also complete a task step and auto set the Completed Units as the Total Units. Further, a warning is shown where Completed Units exceeds the Total Units.
How to Do:
You will need an Execution Type setup (see Project Settings - Entity Settings - Work Package (e.g. IWP) - Select Execution Task Types tab) where the Progress By is set as Quantity. Please note, you will need necessary permissions to manage project settings.
From your IWP (or work package selected) 'Execution' tab in form layout, add the Quantity Tasks, selecting the task type with Progress by Quantity.
Now from the Execution Tasks Progress option on left side, locate the tasks created above, to edit the Completed Units.
Click on the Tick to complete the task...
...and set the Completed units to Match Total Units.
If you have an orange warning triangle - your Completed Units exceeds the Total Units, on the task.
We're Disciplined
Users can now set a “Discipline Category” on their disciplines to manage a parent discipline to discipline relationship.
For example, you might have an engineering discipline as E&I (Electrical and Instrumentation). But for construction, you may want to break out the E&I disciplines to a lower level of detail, say 'High Voltage Electrical', 'Low Voltage Electrical', 'Electrical Heat Tracing', 'Instrumentation'... but want to group them under all under the 'E&I' discipline category. Well now you can.
Note: RFIs currently allow for multiple discipline assignment, so you may see multiple discipline categories displayed as matches the disciplines assigned to the RFI.
How To Use:
To assign the Category you will need to have permission to go into the Project Setup. From there, go to the 'Disciplines' menu item. From the grid, open an existing or add '+' a new discipline entry. On the 'Discipline Details' form, you will see a Category input box to enter your category value.
Now when we have the discipline assigned, the category will be available as a column on the package or RFI grid for example..
In this example we pulled two IWPs that had Electrical and Instrumentation related disciplines assigned.
Also Related to Disciplines...
The disciplines field is now available for import on User Defined Entity Types.
The Matrix
Users can now create disciplines and CWP purposes directly from the CWP matrix.
This conveniently eliminates the need to go back forth with the Project Settings.
The CWP Matrix can be located via the 'Early Planning' project menu option (if turned on for your project).
Depending on the matrix configuration view, (By Purpose or By Discipline selected at the top ) you have a '+' button adjacent to conveniently add a new (Purpose or Discipline) entry.
In this example, we have the CWP Matrix opened in the 'By Purpose' configuration. We click on the '+' button and can now add a new Purpose and will also to added to the CWP matrix. You can then flag if you need a CWP for that purpose generated, within the parent CWA (row).
Alternate 'By Discipline' CWP Matrix configuration view.
System Administrator Notes:
There is a role permission Project Setting, 'Edit CWP Matrix', which can be applied and assigned to users. Project Admins will have permission by default.
Keeping It Simple
Data review entries can now be quick filtered by “Added Components”, “Updated Components”, and “Deleted Components”.
The more detailed Changes column still exists, but we have introduced an additional column 'Change Type' to give a give quick means to filter the changes.
The Data Review screen can be located under the 'Data Management' menu or using the Search at the top.
For Admins: The Model Settings - Version Tracking will need to be switched on to see and track changes in the Data Review grid.
What Remains
Users can now configure the IWP Constraints Bar Chart widget to show the number of hours remaining. The Constraint Type can also be applied to the widget filter. Say you want to pull just the RFI related constraints only.
To Use: Create or edit an existing Dashboard (see under Reporting menu or use search for dashboard at top). Within the dashboard, add (click on + button then 'Add Widget' option) the widget 'IWP Constraints Bar Chart' (can be search within the 'Add Widgets' list window).
With the widget added click on the ellipses/action button and then click on 'Settings.'
Within the widget settings form, locate the 'Value' and select IWP Remaining Hours.
From this output we can see where (by constraint Type) the bulk of the remaining hours are being blocked.
Filters can be applied to home in and you can also click on a bar to drill down to the related constraint data and noted IWPs associated.
Note: O3 additionally offers a 'Blocking IWP Constraints By Type Widget'. This is based on a 'Blocking constraint' being one where the constraint resolved date is after related IWP Planned Start Date.
There's More...
Here is a summary of other changes incorporated into this release...
Rates of Placement on Execution Task Types can now be configured to the ten thousandth of a unit.
When generating IWP report templates, O3 now automatically skips zip file attachments.
Drawing revision update notifications now list the packages affected by the change where the user is the planner user.
Drawing downloads now contain the name drawing name and description in the filename.
The disciplines field is now available for import on User Defined Entity Types and can be set as a mandatory required field in project settings for that user defined entity.
'Labels' is now available as a field on Systems.
You can set an application language on the user profile screen and when adding new users.
Users are now able to change the drawing on their Bill of Material Records when using the 'Source Key' column heading/field in their import.
If you need further details, please reach out to the O3 Team.