Turnover Work Packages - TOP for short (not to be confused with TWP for Testing Work Packages) in the context of AWP (Advanced Work Packaging) as defined by the CII (Construction Industry Institute) is a discrete turnover package aligning Systems with Testing (TWP), Construction (CWP), and Installation (IWP) readiness.
A lot of acronyms here, please use Glossary of Terms for more explanations!
Definition of Final Phases of Projects:
To outline where Turnover sits post construction, let’s also consider Handover and Start-up Phases...
Turnover: This phase involves transferring care, custody and control of a system or subsystem from the EPC contractor to the Owner or Commissioning team. The main objective is to ensure that all project components are completed and meet specified requirements, before formally handing over management to the owner.
Handover: Handover typically refers to the formal transfer of ownership and responsibility of the entire facility from the contractor to the Owner or Commissioning once all project deliverables have been met. This includes presenting all required documentation (warranties, maintenance schedules, operating manuals...), training, and final inspections.
Start-up: Start-up is the phase where installed systems are energized and put into operation for the first time. This involves integrating all components and ensures that systems are functioning as intended under real operating conditions.
Turnover In Practice (EPC / Industrial Project Example)
Prior to the start of Construction, the Ready For Operations Team (RFO) or similar as termed in your organization, are responsible to identify exactly how they would like to receive the completed plant on behalf of the owner operator, typically passed to them from a managing contractor's team responsible for handover (e.g. Commissioning Team / Turnover Team / Systems Completion Team, etc.).
They do this by identifying the turnover systems on Piping and Instrumentation Diagrams (P&IDs) and build a sequence of system turnover activities. The engineering teams are then responsible to identify the systems in the model with the end result being that every component is identified primarily by its association with each turnover system/sub system.
The 3D Model Administrator includes the system allocation attribute in the 3D model file exported to the WFP software (i.e. O3 platform). This allows the Workface Planners to view turnover systems in preparation for testing and system completions. The Workface Planners can then support the Turnover Coordinator by utilizing the WFP software to display systems and progress.
So how do I make a TOP?
The contents of a TOP package vary by project, scope and package requirements, but a comprehensive and well-designed TOP typically includes some or all of the following:
A concise description of the Turnover scope.
Which System and Sub System it pertains to.
As-Built Drawings: These documents should accurately represent the completed construction, changes made during the project, and any modifications from the original design. Drawings should assist illustrating the boundary limits of the turnover package scope.
Equipment / Component Lists: Comprehensive lists of all installed equipment, including relevant models, serial numbers, and suppliers, included in the Turnover Package.
Include any temporary isolations or blockouts, lockouts, or plugs that must be removed prior to commissioning by the owner.
Safety Reports / Documentation.
Certificates of Inspection and Approval: These verify the TOP scope, etc. has passed all required inspections and complies with relevant regulations and codes.
Start-up Sequence Information.
Punch List Items (Type C) Clearance.
Schedule: Dates per agreed Turnover Plan / Systems Completion Schedule.
Contact Information.
The following tend to be more aligned with Handover, but could be considered in Turnover:
Operating Manuals: Detailed guides for all major equipment and systems, outlining operation procedures and maintenance schedules to ensure smooth ongoing operation.
Warranties and Guarantees: Documentation that outlines warranties provided on materials, products, and workmanship used throughout the project.
Maintenance Schedules: Detailed schedules provided for the ongoing maintenance of key systems and components to ensure longevity and efficiency.
Material and Finish Schedules: Specifications and details about materials and finishes used in the project to aid in maintenance and future modifications.
Training Materials: Instructions and materials aimed at training the owners’ staff on operating the systems and equipment installed during the project.
Building Information Modeling (BIM) Data: If applicable, providing BIM models can assist facility management and future upgrades.
Keys and Access Control: Ensure all access points are covered, typically involving multiple complete sets of keys or access devices.
Level of Detail - Other considerations - what level of detail does the TOP package represent - such as will it be a Turnover by Sub System, segregated parts of a sub system or a parent System if granularity of detail is appropriate. This will likely be in conjunction with the aforementioned RFO Team requirements.
Final Thoughts and Why O3?
O3 has the necessary toolset built into the platform, out the box to support the Turnover / System Completions teams.
O3 Supports:
A means to define and manage the TOP packages, with the necessary attributes to classify, status, schedule and progress the TOP packages.
Development Steps can be tracked such as outlining what needs to be achieved to build your TOP packages successfully.
Manage the Component and Materials tied to the TOP package.
Ability to build TOPs by selecting components directly from the 3D Model.
Tracking outstanding punch list items.
Indicate what Documents and Drawings are part of the package.
Generate a list of deliverable / outcome expectations of the package to fulfil before closing the package out.
Manage those known roadblocks and unknown challenges as they occur using O3's comprehensive constraints tools, where you can assign accountability to resolve or mitigate obstacles and expedite package execution.
Put in approval workflows to ensure your checks and balances have taken place.
List your Execution Tasks to manage package progress.
Attach any useful documents in various file types.
Use our integration tools to pull in data or updates or export data as required.
Use our reporting tools, such as dashboards to understand how your TOP packages are progressing across the project.