Make sure you're using the correct version of O3! The version number is located in the bottom left corner!
If you don't see version number 25.11 in the bottom-left corner, please clear your browser's cache and refresh.
Table of Contents
Are You Ready?
We added a 'Construction Readiness Assessment' dashboard template.As Clear As A Bell
The Bell icon will now highlight 'Watcher' updates.Moving On
Yes, you can now move the form sections around when customizing form layouts!Task Master
Team board tasks can now be converted to approvals on entities (RFIs, IWPs...).Flex Those Import Muscles
Data managers can now manage imports from spreadsheets with multiple sheets. Users can specify which sheet (Excel imports) they would like to import, which row contains the header fields, and where the data starts.We Know What you Mean!
The global search has been updated to find similar entities and account for misspellings.Chart A Path
A new "CWP Components Bar Chart" is available to report on component counts by CWP and display the count of components that have been packaged.We have a new (model) post-sync action available to only update the component task backlog following a model update (and exclude the Material BOM update).
Scheduled exports will now use the project time zone for date-time fields.
Lets Get Coordinated
Coordinator 1 - Coordinator 4 fields are now available on IWPs.A time in status calculation is now available as a column on the RFI grid,
as well as a new RFI distribution chart based on time spent in a particular status.
See below for details and use the above table links above to jump to a topic of interest.
Are You Ready?
We added a 'Construction Readiness Assessment ' dashboard and team board template to get you started.
Dashboard Template - available when creating a new dashboard:
Team Board Template - available when creating a new Board:
As Clear As A Bell
The Bell icon will now highlight 'Watcher' updates using the red dot. As before, for direct assignments, a count will be shown within the red dot.
Click on the bell to open your in-app inbox.
To get a watcher notification enabled:
First, you will need to turn on the type of notifications that are prompted. Go to your Notification Settings options via the person icon. Select Notification Settings from the menu, then select Watchers tab and then go to the entity (such as IWPs) you want to be notified on and select 'On' with the On/Off toggle.
Second, you will need to use the watcher (eye) icon on the specific entity record you wish to track updates on. So for example, if you want to track IWP 5, go that record via the IWP grid, open in form layout view and at the top of screen click the 'eye' icon button.
1. Setting Your Watcher Entity Applicable Entities you want to be notified on
2. Choosing which Entity records you want to keep an eye on (watch)
Want More?
Watchers: Want to know more about tracking items of interest in O3?
Click here
Moving On
You can now move the form sections around when customizing form layouts.
Want to move that Engineering Review section above the Construction Review section? Now you can!
How To: Click on the Form layout button with the form view (e.g. open a record from the grid). Then click on Edit Layout from the menu.
Go the tab or main form view and locate the sections. From there you will see a button or buttons to move the section up / down as appropriate (i.e. you will not see move up option for first section or move down for last section).
Task Master
Team board tasks can now be converted to approvals on entities (e.g RFIs, IWPs...).
Open a team board and then open the task you want to convert. With the task open click on the action menu (vertical ellipses) and then on the 'Convert to Approval'.
Flex Those Import Muscles
Data managers can now manage imports from spreadsheets with multiple sheets. Users can specify which sheet (Excel imports) they would like to import, which row contains the header fields and where the data starts.
Note: Header Row and Data Start Row can also be applied to CSV file imports!
O3 Imports now have the additional options to indicate where the data is extracted from within the import file...
We Know What you Mean!
The global search has been updated to find similar entities and account for misspellings.
The global search can be found at the top of the O3 screen.
Chart A Path
A new "CWP Components Bar Chart" is available to report on component counts by CWP and display the count of components that have been packaged.
This widget can be added to your Dashboard, and then use the widget settings to allow for different groupings and filters, etc.
Just the Backlog
A new post-sync action is available to update the component task backlog following a model update. The Bill of Materials (BOM) update will continue to update the component task backlog, but this separate option will allow for additional flexibility when the BOM does not need to be updated.
The action is called 'Refresh Component Task Backlog'.
The Post Sync Action can be configured (see below screen grab) by System and Project Admins under Project Settings - Integrations - open /add the Integration and go to the Sync tab. From there, see the Post Sync Actions configuration.
For further support in this area - please email support@o3.solutions or use the in-app messenger.
Note the existing 'Refresh BOM With Components' action will also run the task backlog update!
It's Time
Scheduled exports will now use the project time zone for date-time fields.
To set the Project Time Zone: Go to the System Admin module. Go to Project Admin - Projects. Open project from the grid and in form layout go to the 'Details' tab and navigate to the Project Time Zone (you will need to be an O3 System Admin to change project time zone).
Lets Get Coordinated
We have added Coordinator, Coordinator 2, Coordinator 3 and Coordinator 4 fields to support IWP supervision.
The Coordinator fields will be linked to an existing O3 User Name.
If not available by default, you may need to edit your IWP form layout as applicable.
Example: here we have added a Coordination Group section in the form layout and added the new fields. You can also add these to your grid layouts.
Time In Status
We have added two enhancements to help track an monitor RFI time in status.
First, we added a time in status calculation column, which is available on the RFI grid.
Example of RFI 'Days in Status' column on RFI grid.
Secondly we added a new RFI distribution chart (dashboard widget) to show the time spent in a particular status.
Example: Here we have added the 'RFI Entity Status History Days In Status Distribution Chart' widget to a dashboard. For settings, we chose the 'Field Request Submitted' status and used the Bin - Bound option settings for durations up to 100 (Max) with 10 day (Bin Width/Size) groups.