Overview
Work Management is an O3 Solutions offering that enables projects to be run without the recommended AWP (Advanced Work Packaging) approach, but still use the O3 user interface and auxiliary project management functionality and tools within O3 to run a project.
Work Management is based on a WBS (Work Breakdown Structure) with Work Orders approach. The WBS provides the coding/work organization structure, and the Work Orders represent the work tasks/activities against the WBS to take place.
Why Would I Use Work Management Instead of AWP?
The WBS and Work Orders approach is older than AWP and some organizations might still use this as the basis for project management. Their WBS structure may be well established, easily understood (familiar) and difficult to migrate away from at this time.
Some organizations may find the AWP terminology incompatible with their industry or business model.
A WBS supports both deliverable and phase based projects.
Some organization might be on the path to AWP, but are not yet ready to fully commit, and/or have a mixture of AWP and Work Management based projects.
From a managing EPC contractor perspective, the owner operator (client) may dictate the use of Work Management over AWP (such as for above reasons).
With O3 accommodating both approaches, all your projects can be stored and managed under one roof, regardless of the project management approach you prefer. We would recommend the AWP path, but we understand its not suitable for everyone or timing might not be right.
If you are undecided or want more information about AWP, please reach out (support@o3.solutions) and also review our AWP Getting Started article by Clicking here.
Work Management Broken Down
For those unfamiliar, lets explain what a WBS and Work Order are...
WBS Definition:
A WBS (Work-Breakdown Structure) in project management and systems engineering is a breakdown of a project into smaller components*. It's a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
So, a WBS will typically be broken out like an organization chart in appearance, but should not be organization based. The WBS is work scope focused and not responsibility focused!
Each level of the WBS structure represents a greater level of detail you wish to break out the work scope of the project and assign tasks (Work Orders) against. Typically you would have 3 to 5 levels as project requires.
The WBS levels need to be defined and fixed before the WBS Components are defined and Work Orders are established.
* In a Work Breakdown Structure (WBS), each part is typically referred to as a
component or element. These components represent the various deliverables, or work packages that need to be completed as part of a project. In some contexts, especially in more technical or software-related fields, these parts might also be called nodes. Both terms are generally acceptable, but "component" or "element" is more commonly used in project management.
Work Orders Definition:
Having established the WBS (coding structure) we can now assign tasks/activities that will fulfil the WBS component objective. These are represented by 'Work Orders'.
For example, a WBS component might be 'Build Security Building West Gate'. The Work Orders might include 'Clear and Excavate Site', 'Lay Foundations and Underground Services', 'Build Walls', 'Install Roof', '1st Fix', '2nd Fix', 'Final Finish/Clean'', "Hook ups', 'Final Inspection'... The Work Order may be split to support multiple contractors/disciplines.
The Work Orders can also tie in materials, (sub) execution tasks, constraints and approvals, as well as associated documents and engineering drawings to support the Work Order.
Example WBS and Work Order Set-up:
According to the example below, the Project typically sits at the top (level 1) and then we breakdown the project scope into its main component parts (level 2). Typically, we then sub divide that into more specific components (level 3). These may again be broken down into further levels (level 4, 5, 6...) of detail as required.
In O3 - As the WBS will be created within a Project - Level 1 does not need to be Project (but that is your choice)!
Work Orders are then associated with a WBS component. In O3, the Work Order will need to be a assigned to a component on the lowest level of the structure (if necessary, if a particular component is not being broken out like others, consider repeating the component on to the next level/s, until represented on last level of structure!).