What is AWP?
Advanced Work Packaging (AWP) is a construction project planning and execution methodology that organizes work into manageable packages. Typically started in the early Front End Engineering Design (FEED) phase, such as FEL2, the aim is to improve safety, productivity, and predictability of projects. To do this, it aligns engineering, procurement, and construction activities through structured work packages like EWPs, CWPs, and IWPs.
Project Execution Methods
What is the Waterfall method?
The Waterfall project execution approach breaks out the project into phases or tranches of related scope and effort. The term comes from the image that each phase flows into the next, like a waterfall (example below).
What is the Agile method?
The Agile methodology breaks a project into smaller (manageable) parts and adjusts to changing requirements. This approach prioritizes delivering smaller pieces of work regularly, allowing teams to adapt quickly and provide customer value faster.
Is AWP a Waterfall or Agile Method to Project Execution?
Neither. The Project Management Institute (PMI) classifies Advanced Work Packaging (AWP) as a hybrid project delivery methodology, combining elements of both Waterfall and Agile approaches.
AWP uses a Waterfall-style structure in that it defines a clear sequence of phases, Engineering Work Packages (EWPs), Procurement Work Packages (PWPs), and Construction Work Packages (CWPs), which flow logically from one stage to the next. These packages are planned early in the project, providing the predictability and control typical of traditional project execution.
At the same time, AWP embraces Agile-like flexibility through its use of Installation Work Packages (IWPs). These are short-duration, field-ready work packages that allow for adaptive planning and real-time decision-making during execution, much like Agile sprints. Teams can respond to changing conditions on site, prioritize critical scopes, and re-sequence work as needed without disrupting the entire project plan.
By blending the discipline of Waterfall with the responsiveness of Agile, AWP delivers a structured yet flexible framework for managing complex construction projects.
How Did AWP Come About ?
AWP began as an extension to Workface Planning (WFP), which was initially developed in Canada as an effort to reverse declining field productivity by improving execution planning and efficiency. This concept was then extended into a partnership between the Construction Owners Association of Alberta (COAA) and the Construction Industry Institute (CII) (see link at the end of this article).
AWP was recognized as a CII Best Practice in 2015
What is Workface Planning (WFP)?
Workface Planning (WFP) is a construction best practice that involves organizing and delivering all the necessary information, materials, tools, and resources to the work site before work begins. Its primary focuses on creating Installation Work Packages (IWPs)—detailed, discipline-specific plans for tasks typically covering 1–2 weeks of work for a single work crew. The goal of WFP is to ensure crews can perform work safely, efficiently, and without constraints or delays caused by missing equipment, materials, or drawings; ultimately improving productivity and reducing rework. WFP is a key part of the AWP process and is executed during the construction phase of a project.
Can AWP Be Used For The Whole Project Lifecycle?
The short answer is Yes. The AWP methodology was designed to start from the conception of a project and be used throughout the full project’s life-cycle.
How do you Break a Project Down into Smaller Parts?
The Advanced Work Packaging (AWP) process breaks down a project in a structured, phased way that aligns engineering, procurement, and construction activities. Similar to a Work Breakdown Structure (WBS), the top layer represents the overall project. From there, the project is divided into Construction Work Areas (CWAs)—geographic zones that help define where work will take place.
Within each CWA, the scope is organized into Construction Work Packages (CWPs), which group related work by discipline (e.g., piping, structural, electrical). Each CWP is then broken down into Installation Work Packages (IWPs)—short-term, detailed packages containing everything a crew needs to execute about 1–2 weeks of work, this would include drawings, materials, permits, and safety documentation.
This structure supports efficient planning and execution during bulk construction. But AWP doesn’t stop there. It also supports system completion and turnover. This phase starts with defining Turnover Packages (TOPs), which can be area-based (like structural) or system-based (like Instrument Air). System-based TOPs often span multiple CWAs, so they’re not tied to a single location.
To manage large or complex systems, projects may introduce Sub-Systems to further break the work down. Each system or sub-system is then divided into Test Work Packages (TWPs), which contain all the information required for testing teams to confirm compliance with the Internal Testing Procedures (ITPs).
The AWP process, breaks a project into smaller, manageable parts by using a layered approach, starting with geographical areas and progressing through discipline-specific scopes, detailed field-ready work packages, and ultimately testing and turnover. This structure enhances visibility, reduces constraints, and ensures smoother project delivery from start to finish.
Getting Started - Early Planning
Getting started with Advanced Work Packaging (AWP) begins in the Early Planning phase, typically during FEL2, when key decisions are made that shape the entire execution strategy. This stage is led by construction and supported by engineering, procurement, and project controls departments. Some of the key early planning activities include:
Defining Construction Work Areas (CWAs)
Establishing package governance and responsibilities (RACI)
Developing the Path of Construction (POC)
Initiating Engineering Work Packages (EWPs) and Procurement Work Packages (PWPs)
Creating the framework for a Level 3 resource-loaded project schedule
One of the most critical early deliverables is the Path of Construction (POC). The POC outlines the ideal sequence of construction based on site layout, constraints, and project priorities. We recommend breaking POC into Four phases: early works, main construction, system completion, and demobilization, since each phase has distinct site conditions and requirements.
Early Works: Focus on preparing the site—laydown areas, temporary facilities, and access roads. These can be mapped using aerial imagery and help sequence enabling work efficiently.
Main Construction: Use a detailed plot plan to define CWAs, which are then divided into Construction Work Packages (CWPs) by discipline. These boundaries help communicate the construction sequence and establish work priorities.
System Completion: This phase focuses on transitioning from area-based bulk construction to system-based work. It involves aligning construction completion with commissioning priorities by introducing Turnover Packages (TOPs) and Test Work Packages (TWPs). Systems often span multiple CWAs, so coordination becomes essential to ensure that interconnected scopes—like piping, electrical, and instrumentation—are completed and available for testing. Proper planning during this phase supports early system turnover, reduces rework, and accelerates the path to mechanical completion.
Demobilization: Often overlooked, this phase should include removal of temporary infrastructure and site restoration. Construction and the client must align on this scope early to avoid delays or cost surprises later.
Throughout FEL2 and FEL3, the POC will evolve through collaboration and input from engineering and procurement. The ultimate goal is to develop a fully aligned, resource-loaded Level 3 schedule before Final Investment Decision (FID). Project Controls uses the POC to drive the sequencing of EWPs, PWPs, and VWPs (Vendor Work Packages) to support the needs of construction.
By establishing this foundation early, the project is set up for better alignment, smoother execution, and more predictable outcome.
What Kind of 'Work Packages' Will I Need?
After the Construction Work Areas (CWAs) are defined, each area is broken out into Construction Work Packages (CWPs). These CWPs are typically organized by discipline (e.g., Civil, Piping, Mechanical, Electrical) or by purpose (e.g., Above-Ground Concrete, Underground Electrical Cabling). Each CWP represents a major scope of work that can be planned, tracked, and measured.
For teams just starting their AWP journey, we recommend keeping it simple by focusing on the core package types:
Construction Work Areas (CWAs) – Geographical scopes of work.
Engineering Work Packages (EWPs) – Deliverables from engineering needed to support CWPs.
Procurement Work Packages (PWPs) – Materials and equipment required to execute CWPs.
Construction Work Packages (CWPs) – Discipline-based groupings of construction scope.
Installation Work Packages (IWPs) – Detailed field-ready packages used by crews, typically covering 1-2 weeks of work.
Once your team gains experience executing projects using these foundational packages, you can begin to expand your approach by incorporating more specialized work packages, such as:
Design Work Packages (DWPs) – Used in design-heavy scopes where pre-EWP engineering effort needs to be tracked.
Scaffold Work Packages (SWPs) – To plan and track scaffolding scope, often used as enablers for multiple IWPs.
Test Work Packages (TWPs) – For system-based commissioning and startup activities.
Turnover Packages (TOPs) – For client handover and project completion.
To further support predictability and planning, it’s important to integrate key project documentation into your AWP work processes. O3 refers to these as Custom Entity Types and can be used to support the documentation process of various types of communication found on a project. Examples include:
NCRs (Non-Conformance Reports)
PDNs (Project Deviation Notices)
TQs (Technical Queries)
FCNs (Field Change Notices)
SIs (Site Instructions)
Each of these contributes valuable visibility into potential constraints and changes encountered on a project, helping improve schedule certainty and decision-making.
In O3 you can now create the types you need and if you use Change Order, Variation Order or DCN (Design Change Notice) instead of a PDN (or in addition to), the choice is yours.
RFIs (Requests for Information) are another example (these are pre defined in O3) as a valuable project tracking document and tool.
What next ? Adapting AWP to Fit Your Project Strategy
Now that you understand the types of work packages and supporting documentation commonly used in AWP, the next step is determining how to apply these tools within your project’s contracting model and delivery approach.
Whether you're responsible for only a portion of the project, like construction or commissioning, or managing the full project lifecycle from engineering through turnover, it’s important to align your AWP strategy accordingly.
For teams just starting out, focusing on core packages like CWAs, EWPs, PWPs, CWPs, and IWPs provides a strong foundation. But as your team gains experience and your project needs evolve, expanding your use of package types and integrated documentation will offer greater control, visibility, and alignment with construction priorities.
O3 supports this scalability by offering a robust AWP platform that not only includes all common work package types but also allows you to define custom ones that align with your specific work processes and contracting approach. Whether you're executing lump sum, reimbursable, or hybrid contracts, O3 helps you configure AWP to match your structure—ensuring consistency, accountability, and predictability across all phases of the project.
In short, your AWP journey doesn’t need to be overly complex at the start, but having the right tools and flexibility in place allows your organization to grow and adapt over time.
Example Work Package Types:
Work Package Type | Phase | Description |
CWA | All | A geographic work zone used to divide the project site into manageable areas. Serves as the foundation for organizing CWPs and other work packages. |
EWP | Engineering | Typically aligned on a one to one basis with a CWP (so e.g. based on CWA and Discipline/Purpose breakdown). |
DWP | Engineering | Where you need to break those EWPs into smaller packages, a DWP can be used. |
VWP | Engineering | Vendor Work Packages are used to gather related documents, drawings and feedback as well as to link to Vendor Data, such as data / specification sheets etc. |
PWP | Procurement | Once Engineering has determined a Bill of Materials (BOM), Procurement will start to requisition, order and expedite materials to support construction / installation. PWPs can be established and tied to EWPs to group common requirements |
IWP | Construction | These sit under the CWP and there can be multiple IWPs to one CWP. |
SWP | Construction, Pre-Commissioning & Commissioning | If you need scaffolding and you have a dedicated scaffolding contractor they can manage the related Scaffolding Requests and Scaffold equipment against Scaffolding Work Packages. |
System | Construction, Pre-Commissioning & Commissioning | A functional grouping of assets (e.g., Instrument Air, Firewater). Used to organize commissioning and turnover scopes. |
TWP | Pre-Commissioning | Contains all test procedures, documentation, and ITP compliance required to test and validate a portion of a system. Types of test can include Hydro or Pneumatic test for Piping. Continuity, Megger, Grounding, Hi-Pot, Loop Checks, Function, Interlock and Trip Logic, Lightning Protection for Electrical. |
TOP | Handover/Turnover | Final handover package that includes all necessary documents to transfer Care, Custody, and Control over to the client. This would include Drawings, As-Builts, Test Results, Clarification of Design and Certifications. |
Further Sources of Information on AWP
Please note any external web links provided from this article are provided in good faith, but are not managed by O3 Solutions. Please use at own risk and discretion.
CONSTRUCTION INDUSTRY INSTITUTE (CII)
CII is the primary source for AWP information, and the organization that lists AWP as a Best Practice.
Any of the information below relating to CII is for members only. A current CII membership is required to open / download the research papers and tools.
Website
The AWP information on this ‘landing page’ is grouped into three categories:
• Discover – For new users and those seeking information about AWP.
• Engage – Tools and information for those looking to implement AWP.
• Expand – For organizations looking to expand AWP across their portfolio.
There are several publications or tools within each category:
Construction Owners Association of Alberta (COAA)
Owner-led membership bringing together Alberta's heavy industrial construction industry.
Website
https://coaa.ab.ca/